| Assessment Year | 2024 |
|---|---|
| Principal Product | Commercial Screen Printing |
| NAICS | 323113: Commercial Screen Printing |
| SIC | 2759: Commercial Printing, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 189 |
| Plant Area |
225,000
ft2
|
| Annual Production | 500,000
units
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | West Virginia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $229,051 | 3,435,403 |
kWh
|
$0.067 |
| Electricity Demand | $218,881 | 14,185 |
kW-mo/yr
|
$15.43 |
| Electricity Fees | $5,197 | - |
|
- |
| LPG | $33,968 | 1,995 |
MMBtu
|
$17.03 |
| TOTAL YEARLY COSTS | $487,097 | |||
| RECOMMENDED SAVINGS* | $216,725 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $22,360 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | LPG Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $163,920 | $663,966 |
$117,445
1,760,790
kWh
|
$46,475
-
kW-mo/yr
|
- | - | |
| 02 | 2.7232: Replace existing hvac unit with high efficiency model | $24,663 | $80,657 |
$18,445
276,544
kWh
|
$6,218
-
kW-mo/yr
|
- | - | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $12,514 | $29,651 |
$8,656
129,768
kWh
|
$3,858
-
kW-mo/yr
|
- | - | |
| 04 | 2.7135: Install occupancy sensors | $6,065 | $25,395 |
$4,013
60,164
kWh
|
$2,052
-
kW-mo/yr
|
- | - | |
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,602 | $252 |
$1,801
26,999
kWh
|
$801
-
kW-mo/yr
|
- | - | |
| 06 | 2.3212: Optimize plant power factor | $1,934 | $4,653 | - | - | $1,934 | - | |
| 07 | 2.7241: Install outside air damper / economizer on hvac unit | $1,456 | $6,768 |
$1,194
17,904
kWh
|
$262
-
kW-mo/yr
|
- | - | |
| 08 | 2.4221: Install compressor air intakes in coolest locations | $1,305 | $1,422 |
$474
7,106
kWh
|
$508
-
kW-mo/yr
|
- |
$323
-
MMBtu
|
|
| 09 | 2.4224: Upgrade controls on compressors | $1,087 | $3,439 |
$871
13,064
kWh
|
$216
-
kW-mo/yr
|
- | - | |
| 10 | 2.4239: Eliminate or reduce compressed air usage | $664 | $1,243 |
$463
6,940
kWh
|
$201
-
kW-mo/yr
|
- | - | |
| 11 | 2.4231: Reduce the pressure of compressed air to the minimum required | $515 | $26 |
$361
5,408
kWh
|
$154
-
kW-mo/yr
|
- | - | |
| TOTAL RECOMMENDED | $216,725 | $817,472 |
$153,723
2,304,687
kWh
|
$60,745
-
kW-mo/yr
|
$1,934 |
$323
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $22,360 | $56,567 |
$15,294
229,279
kWh
|
$7,066
-
kW-mo/yr
|
- | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | LPG Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs