Assessment Year | 2008 |
---|---|
Principal Product | Marbles |
NAICS | 339930: Doll, Toy, and Game Manufacturing |
SIC | 3944: Games, Toys, and Children's Vehicles, Except Dolls and Bicycles |
Sales Range | $1 M to 5M |
# of Employees | 25 |
Plant Area |
45,000
ft2
|
Annual Production | 850,000
lb
|
Production Hrs. Annual | 2,080
hrs
|
Location (State) | West Virginia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $6,951 | 188,576 |
kWh
|
$0.037 |
Electricity Demand | $5,775 | 787 |
kW-mo/yr
|
$7.34 |
Electricity Fees | $1,153 | - |
|
- |
Natural Gas | $103,108 | 10,781 |
MMBtu
|
$9.56 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $15,338 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $14,217 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.2511: Insulate bare equipment | $11,312 | $2,971 |
$356
9,669
kWh
|
- |
$10,956
-
MMBtu
|
|
02 | 3.1161: Eliminate/reduce an operation | $1,977 | $1,750 |
$1,192
32,314
kWh
|
$785
-
kW-mo/yr
|
- | |
03 | 2.7144: Install spectral reflectors / delamp | $825 | $140 |
$472
12,779
kWh
|
$353
-
kW-mo/yr
|
- | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $747 | $1,927 |
$526
14,251
kWh
|
$221
-
kW-mo/yr
|
- | |
05 | 2.2437: Recover waste heat from equipment | $296 | $600 | - | - |
$296
-
MMBtu
|
|
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $181 | $60 |
$84
2,281
kWh
|
$97
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $15,338 | $7,448 |
$2,630
71,294
kWh
|
$1,456
-
kW-mo/yr
|
$11,252
-
MMBtu
|
||
TOTAL IMPLEMENTED | $14,217 | $6,708 |
$2,158
58,515
kWh
|
$1,103
-
kW-mo/yr
|
$10,956
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs