| Assessment Year | 2003 |
|---|---|
| Principal Product | Processed Vegetables |
| NAICS | 311411: Frozen Fruit, Juice, and Vegetable Manufacturing |
| SIC | 2037: Frozen Fruits, Fruit Juices, and Vegetables |
| Sales Range | $10 M to 50M |
| # of Employees | 124 |
| Plant Area |
289,874
ft2
|
| Annual Production | 25,000,000
lb
|
| Production Hrs. Annual | 4,704
hrs
|
| Location (State) | Delaware |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $645,963 | 19,598,465 |
kWh
|
$0.033 |
| Electricity Demand | $425,519 | 50,580 |
kW-mo/yr
|
$8.41 |
| Electricity Fees | $57,200 | - |
|
- |
| Natural Gas | $68,542 | 11,291 |
MMBtu
|
$6.07 |
| Fuel Oil #6 | $171,303 | 43,284 |
MMBtu
|
$3.96 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $213,193 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $84,692 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Fuel Oil #6 Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 3.5311: Recover and reuse waste material | $81,748 | $300,000 | - | - |
$874
-
MMBtu
|
$874
-
MMBtu
|
- |
$80,000
-
lb
|
- | |
| 02 | 2.2135: Repair and eliminate steam leaks | $27,508 | $204 | - | - |
$13,754
-
MMBtu
|
$13,754
-
MMBtu
|
- | - | - | |
| 03 | 2.2113: Repair or replace steam traps | $23,200 | $1,000 | - | - |
$11,600
-
MMBtu
|
$11,600
-
MMBtu
|
- | - | - | |
| 04 | 3.4151: Minimize water usage | $21,233 | $3,420 | - | - |
$9,273
-
MMBtu
|
$9,274
-
MMBtu
|
$2,686
-
Tgal
|
- | - | |
| 05 | 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary | $18,480 | $504 |
$11,761
327,867
kWh
|
$7,034
-
kW-mo/yr
|
- | - | - | - | $(-315.0) | |
| 06 | 2.2414: Use waste heat from hot flue gases to preheat | $15,072 | $1,915 | - | - |
$7,536
-
MMBtu
|
$7,536
-
MMBtu
|
- | - | - | |
| 07 | 2.2162: Reduce excess steam bleeding | $9,439 | $37,100 |
$5,907
164,666
kWh
|
$3,532
-
kW-mo/yr
|
- | - | - | - | - | |
| 08 | 2.4231: Reduce the pressure of compressed air to the minimum required | $4,418 | $42 |
$2,764
77,125
kWh
|
$1,654
-
kW-mo/yr
|
- | - | - | - | - | |
| 09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,387 | $7,590 |
$2,407
67,184
kWh
|
$1,980
-
kW-mo/yr
|
- | - | - | - | - | |
| 10 | 2.2511: Insulate bare equipment | $3,709 | $258 |
$2,321
64,706
kWh
|
$1,388
-
kW-mo/yr
|
- | - | - | - | - | |
| 11 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,990 | - |
$1,871
52,158
kWh
|
$1,119
-
kW-mo/yr
|
- | - | - | - | - | |
| 12 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $674 | $242 |
$420
11,826
kWh
|
$254
-
kW-mo/yr
|
- | - | - | - | - | |
| 13 | 2.4234: Cool compressor air intake with heat exchanger | $335 | $1,960 |
$210
5,824
kWh
|
$125
-
kW-mo/yr
|
- | - | - | - | - | |
| TOTAL RECOMMENDED | $213,193 | $354,235 |
$27,661
771,356
kWh
|
$17,086
-
kW-mo/yr
|
$43,037
-
MMBtu
|
$43,038
-
MMBtu
|
$2,686
-
Tgal
|
$80,000
-
lb
|
$(-315.0) | ||
| TOTAL IMPLEMENTED | $84,692 | $9,598 |
$21,124
589,040
kWh
|
$13,175
-
kW-mo/yr
|
$25,354
-
MMBtu
|
$25,354
-
MMBtu
|
- | - | $(-315.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Fuel Oil #6 Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs