ITAC Assessment: WV0255
ITAC logo
ITAC Assessment: WV0255
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2003
Principal Product Polystyrene plastic pellets
NAICS 325211: Plastics Material and Resin Manufacturing
SIC 2821: Plastics Materials, Synthetic Resins, and Nonvulcanizable Elastomers
Sales Range $50
M
to 100
M
# of Employees 70
Plant Area 820,000
ft2
Annual Production 400,000,000
lb
Production Hrs. Annual 8,760
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $478,058 30,066,506
kWh
Electricity Demand $530,587 49,705
kW-mo/yr
Natural Gas $548,258 112,800
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $415,587 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $63,431

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (haz) Savings Personnel Changes Savings Primary Raw Material Savings
01 2.4221: Install compressor air intakes in coolest locations $1,219 $310 $760
37,036
kWh
$459
-
kW-mo/yr
- - - -
02 2.4231: Reduce the pressure of compressed air to the minimum required $1,774 $100 $1,122
54,528
kWh
$652
-
kW-mo/yr
- - - -
03 2.2614: Use cooling tower or economizer to replace chiller cooling $965 $2,700 $742
36,039
kWh
$223
-
kW-mo/yr
- - - -
04 2.2625: Chill water to the highest temperature possible $2,019 $200 $1,260
61,237
kWh
$759
-
kW-mo/yr
- - - -
05 2.4111: Utilize energy-efficient belts and other improved mechanisms $7,236 $2,025 $4,516
219,457
kWh
$2,720
-
kW-mo/yr
- - - -
06 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary $42,452 $2,000 $26,871
1,305,608
kWh
$16,181
-
kW-mo/yr
- - $(-600.0) -
07 2.2414: Use waste heat from hot flue gases to preheat $27,449 $2,455 - - $27,449
-
MMBtu
- - -
08 2.1233: Analyze flue gas for proper air/fuel ratio $10,094 $1,000 - - $10,094
-
MMBtu
- - -
09 2.7142: Utilize higher efficiency lamps and/or ballasts $1,875 - $1,170
43,169
kWh
$705
-
kW-mo/yr
- - - -
10 2.2162: Reduce excess steam bleeding $4,622 $80,000 $2,884
140,160
kWh
$1,738
-
kW-mo/yr
- - - -
11 3.4151: Minimize water usage $315,882 $25,000 $1,400
67,976
kWh
- - $34,482
-
gal
- $280,000
TOTAL RECOMMENDED $415,587 $115,790 $40,725
1,965,210
kWh
$23,437
-
kW-mo/yr
$37,543
-
MMBtu
$34,482
-
gal
$(-600.0) $280,000
TOTAL IMPLEMENTED $63,431 $5,125 $33,679
1,622,762
kWh
$20,258
-
kW-mo/yr
$10,094
-
MMBtu
- $(-600.0) -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (haz) Savings Personnel Changes Savings Primary Raw Material Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs