Assessment Year | 1999 |
---|---|
Principal Product | Fiber filters |
NAICS |
n/a
|
SIC | 3564: Industrial and Commercial Fans and Blowers and Air Purification Equipment |
Sales Range | $10 M to 50M |
# of Employees | 125 |
Plant Area |
100,000
ft2
|
Annual Production | 357,000
thousand feet
|
Production Hrs. Annual | 8,568
hrs
|
Location (State) | West Virginia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $156,806 | 3,606,389 |
kWh
|
$0.043 |
Natural Gas | $267,372 | 75,878 |
MMBtu
|
$3.52 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $91,943 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $81,625 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | LPG Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,038 | $30 |
$2,038
71,805
kWh
|
- | - | - | - | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,261 | $132 |
$1,261
44,549
kWh
|
- | - | - | - | - | |
03 | 2.7241: Install outside air damper / economizer on hvac unit | $1,997 | $1,290 |
$1,997
70,340
kWh
|
- | - | - | - | - | |
04 | 2.1331: Burn a less expensive grade of fuel | $4,974 | $6,400 | - |
$(-3,387.0)
-
MMBtu
|
$8,361
-
MMBtu
|
- | - | - | |
05 | 2.2511: Insulate bare equipment | $3,844 | $390 | - |
$3,844
-
MMBtu
|
- | - | - | - | |
06 | 2.2437: Recover waste heat from equipment | $947 | $616 | - |
$947
-
MMBtu
|
- | - | - | - | |
07 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $740 | $420 |
$740
26,084
kWh
|
- | - | - | - | - | |
08 | 2.2442: Preheat combustion air with waste heat | $1,619 | $3,500 | - |
$1,619
-
MMBtu
|
- | - | - | - | |
09 | 3.3131: Use evaporation to concentrate material | $1,854 | $1,075 | - | - | - |
$1,854
-
Tgal
|
- | - | |
10 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $49,719 | $11,000 | - | - | - | - |
$49,719
-
lb
|
- | |
11 | 4.111: Add equipment/ operators to reduce production bottleneck | $22,950 | - | - | - | - | - | - | $22,950 | |
TOTAL RECOMMENDED | $91,943 | $24,853 |
$6,036
212,778
kWh
|
$3,023
-
MMBtu
|
$8,361
-
MMBtu
|
$1,854
-
Tgal
|
$49,719
-
lb
|
$22,950 | ||
TOTAL IMPLEMENTED | $81,625 | $13,887 |
$3,258
114,889
kWh
|
$3,844
-
MMBtu
|
- |
$1,854
-
Tgal
|
$49,719
-
lb
|
$22,950 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | LPG Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs