| Assessment Year | 1998 |
|---|---|
| Principal Product | Marbles & hand blown glass |
| NAICS |
n/a
|
| SIC | 3231: Glass Products, Made of Purchased Glass |
| Sales Range | $1 M to 5M |
| # of Employees | 150 |
| Plant Area |
250,000
ft2
|
| Annual Production | 4,912
ton
|
| Production Hrs. Annual | 8,736
hrs
|
| Location (State) | West Virginia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $32,709 | 541,618 |
kWh
|
$0.060 |
| Natural Gas | $341,325 | 97,703 |
MMBtu
|
$3.49 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $214,521 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $62,954 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.2514: Cover open tanks | $38,890 | $16,000 |
$38,890
-
MMBtu
|
- | - | |
| 02 | 2.2511: Insulate bare equipment | $186 | $80 |
$186
-
MMBtu
|
- | - | |
| 03 | 2.2442: Preheat combustion air with waste heat | $5,769 | $825 |
$5,769
-
MMBtu
|
- | - | |
| 04 | 2.8113: Purchase gas directly from a contract gas supplier | $47,874 | - | - | - | $47,874 | |
| 05 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $3,177 | $11,000 | - |
$3,177
-
lb
|
- | |
| 06 | 4.652: Replace existing equipment with more suitable substitutes | $9,125 | $150 | - | - | $9,125 | |
| 07 | 4.122: Develop standard procedures to improve internal yields | $109,500 | $16,500 | - | - | $109,500 | |
| TOTAL RECOMMENDED | $214,521 | $44,555 |
$44,845
-
MMBtu
|
$3,177
-
lb
|
$166,499 | ||
| TOTAL IMPLEMENTED | $62,954 | $1,055 |
$5,955
-
MMBtu
|
- | $56,999 | ||
| Yearly Savings* | Imp'd Cost* | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs