ITAC Assessment: WV0148
ITAC logo
ITAC Assessment: WV0148
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Marbles & hand blown glass
NAICS
n/a
SIC 3231: Glass Products, Made of Purchased Glass
Sales Range $1
M
to 5
M
# of Employees 150
Plant Area 250,000
ft2
Annual Production 4,912
ton
Production Hrs. Annual 8,736
hrs
Location (State) West Virginia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $32,709 541,618
kWh
Natural Gas $341,325 97,703
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $214,521 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $62,954

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Natural Gas Savings Solid Waste (non-haz) Savings Administrative Changes Savings
01 2.2514: Cover open tanks $38,890 $16,000 $38,890
-
MMBtu
- -
02 2.2511: Insulate bare equipment $186 $80 $186
-
MMBtu
- -
03 2.2442: Preheat combustion air with waste heat $5,769 $825 $5,769
-
MMBtu
- -
04 2.8113: Purchase gas directly from a contract gas supplier $47,874 - - - $47,874
05 3.6193: Install equipment (eg compactor) to reduce disposal costs $3,177 $11,000 - $3,177
-
lb
-
06 4.652: Replace existing equipment with more suitable substitutes $9,125 $150 - - $9,125
07 4.122: Develop standard procedures to improve internal yields $109,500 $16,500 - - $109,500
TOTAL RECOMMENDED $214,521 $44,555 $44,845
-
MMBtu
$3,177
-
lb
$166,499
TOTAL IMPLEMENTED $62,954 $1,055 $5,955
-
MMBtu
- $56,999
Yearly Savings* Imp'd Cost* Natural Gas Savings Solid Waste (non-haz) Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs