Assessment Year | 1998 |
---|---|
Principal Product | Hand-pressed Glassware |
NAICS |
n/a
|
SIC | 3229: Pressed and Blown Glass and Glassware, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 144 |
Plant Area |
184,000
ft2
|
Annual Production | 0
ton
|
Production Hrs. Annual | 2,125
hrs
|
Location (State) | Pennsylvania |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $124,145 | 2,219,812 |
kWh
|
$0.056 |
Electricity Demand | $34,996 | 6,273 |
kW-mo/yr
|
$5.58 |
Natural Gas | $435,432 | 106,855 |
MMBtu
|
$4.07 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $56,237 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $49,478 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4314: Use synthetic lubricant | $674 | $336 |
$674
16,706
kWh
|
- | - | - | - | - | |
02 | 2.2511: Insulate bare equipment | $92 | $85 | - | - |
$92
-
MMBtu
|
- | - | - | |
03 | 2.2511: Insulate bare equipment | $5,488 | $910 | - | - |
$5,488
-
MMBtu
|
- | - | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $198 | $152 |
$43
1,172
kWh
|
$155
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.2422: Use waste heat from hot flue gases to generate steam | $3,479 | $677 | - | - |
$3,479
-
MMBtu
|
- | - | - | |
06 | 2.1122: Re-size charging openings or add a movable door on equipment | $2,538 | $470 | - | - |
$2,538
-
MMBtu
|
- | - | - | |
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $166 | $40 |
$166
4,103
kWh
|
- | - | - | - | - | |
08 | 3.4156: Use flow control valves on equipment to optimize water use | $650 | $300 | - | - | - |
$650
-
Tgal
|
- | - | |
09 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $1,752 | $90 | - | - | - | - |
$1,752
-
lb
|
- | |
10 | 4.452: Eliminate shift | $8,050 | $75 | - | - | - | - | - | $8,050 | |
11 | 4.432: Cross-train personnel to avoid lost time | $33,150 | $750 | - | - | - | - | - | $33,150 | |
TOTAL RECOMMENDED | $56,237 | $3,885 |
$883
21,981
kWh
|
$155
-
kW-mo/yr
|
$11,597
-
MMBtu
|
$650
-
Tgal
|
$1,752
-
lb
|
$41,200 | ||
TOTAL IMPLEMENTED | $49,478 | $2,353 |
$883
21,981
kWh
|
$155
-
kW-mo/yr
|
$5,488
-
MMBtu
|
- |
$1,752
-
lb
|
$41,200 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs