| Assessment Year | 1998 |
|---|---|
| Principal Product | Dry Dog Food |
| NAICS |
n/a
|
| SIC | 2048: Prepared Feed and Feed Ingredients for Animals and Fowls, Except Dogs and Cats |
| Sales Range | $10 M to 50M |
| # of Employees | 75 |
| Plant Area |
14,000
ft2
|
| Annual Production | 41,000
ton
|
| Production Hrs. Annual | 7,488
hrs
|
| Location (State) | Pennsylvania |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $147,252 | 2,928,253 |
kWh
|
$0.050 |
| Natural Gas | $188,557 | 26,592 |
MMBtu
|
$7.09 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $70,526 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $59,032 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | Water Consumption Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $554 | $440 |
$554
14,361
kWh
|
- | - | - | |
| 02 | 2.4133: Use most efficient type of electric motors | $5,014 | $11,290 |
$5,014
127,491
kWh
|
- | - | - | |
| 03 | 2.2511: Insulate bare equipment | $500 | $290 | - |
$500
-
MMBtu
|
- | - | |
| 04 | 2.7241: Install outside air damper / economizer on hvac unit | $527 | $2,700 |
$527
13,775
kWh
|
- | - | - | |
| 05 | 2.2414: Use waste heat from hot flue gases to preheat | $5,117 | $1,875 | - |
$5,117
-
MMBtu
|
- | - | |
| 06 | 2.2511: Insulate bare equipment | $1,532 | $1,120 | - |
$1,532
-
MMBtu
|
- | - | |
| 07 | 2.2437: Recover waste heat from equipment | $568 | $840 | - |
$568
-
MMBtu
|
- | - | |
| 08 | 3.4115: Recover and reuse cooling water | $1,307 | $1,300 | - | - | - |
$1,307
-
Tgal
|
|
| 09 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $3,975 | $11,000 | - | - | $3,975 | - | |
| 10 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $1,512 | - | - | - | $1,512 | - | |
| 11 | 4.112: Replace old machine with new automatic multi-station tool | $49,920 | $15,000 | - | - | $49,920 | - | |
| TOTAL RECOMMENDED | $70,526 | $45,855 |
$6,095
155,627
kWh
|
$7,717
-
MMBtu
|
$55,407 |
$1,307
-
Tgal
|
||
| TOTAL IMPLEMENTED | $59,032 | $28,140 |
$5,568
141,852
kWh
|
$2,032
-
MMBtu
|
$51,432 | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | Water Consumption Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs