ITAC Assessment: WV0127
ITAC logo
ITAC Assessment: WV0127
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Heat Processing Equipment
NAICS
n/a
SIC 3567: Industrial Process Furnaces and Ovens
Sales Range $10
M
to 50
M
# of Employees 190
Plant Area 102,950
ft2
Annual Production 60
pieces
Production Hrs. Annual 2,210
hrs
Location (State) Pennsylvania

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $36,734 1,226,260
kWh
Electricity Demand $41,365 4,240
kW-mo/yr
Electricity Fees $15,993 -
Natural Gas $61,467 14,287
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $210,692 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,980

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $718 $807 $155
3,517
kWh
$563
-
kW-mo/yr
- - - - -
02 2.4133: Use most efficient type of electric motors $2,628 $4,080 $339
7,913
kWh
$2,289
-
kW-mo/yr
- - - - -
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $243 $480 $243
5,569
kWh
- - - - - -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $391 $200 $391
9,086
kWh
- - - - - -
05 2.7243: Improve air circulation with destratification fans / other methods $19,644 $12,500 $(-88.0)
(-2,052)
kWh
- $19,732
-
MMBtu
- - - -
06 2.6212: Turn off equipment during breaks, reduce operating time $3,192 - - - $3,192
-
MMBtu
- - - -
07 3.2123: Convert to high volume low pressure (hvlp) paint guns $96,588 $16,000 $6,741
156,800
kWh
- - - - $1,463 $88,384
08 3.4111: Use closed cycle process to minimize waste water production $538 $188 - - - $538
-
Tgal
- - -
09 3.5316: Contract a wood pallet recycling company $1,040 $200 - - - - - $1,040 -
10 4.514: Re-arrange equipment layout to reduce handling costs $85,710 $80,000 $2,835
65,944
kWh
- - - $82,875 - -
TOTAL RECOMMENDED $210,692 $114,455 $10,616
246,777
kWh
$2,852
-
kW-mo/yr
$22,924
-
MMBtu
$538
-
Tgal
$82,875 $2,503 $88,384
TOTAL IMPLEMENTED $3,980 $5,567 $1,128
26,085
kWh
$2,852
-
kW-mo/yr
- - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs