Assessment Year | 1997 |
---|---|
Principal Product | Bricks |
NAICS |
n/a
|
SIC | 3297: Nonclay Refractories |
Sales Range | $5 M to 10M |
# of Employees | 53 |
Plant Area |
100,000
ft2
|
Annual Production | 30,000,000
pieces
|
Production Hrs. Annual | 1,989
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $182,787 | 4,965,123 |
kWh
|
$0.037 |
Electricity Fees | $72,720 | - |
|
- |
Natural Gas | $599,616 | 190,656 |
MMBtu
|
$3.15 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $448,178 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $10,060 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Personnel Changes Savings | Administrative Changes Savings | Water Consumption Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $258 | $248 |
$258
4,982
kWh
|
- | - | - | - | |
02 | 2.4133: Use most efficient type of electric motors | $1,663 | $11,400 |
$1,663
32,239
kWh
|
- | - | - | - | |
03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $6,379 | $2,240 |
$6,379
123,974
kWh
|
- | - | - | - | |
04 | 2.4314: Use synthetic lubricant | $422 | $640 |
$422
8,206
kWh
|
- | - | - | - | |
05 | 2.3412: Use waste heat to produce steam to drive a steam turbine-generator | $10,136 | $43,250 |
$16,136
313,599
kWh
|
- | $(-6,000.0) | - | - | |
06 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $900 | $5,000 | - | $(-936.0) | $1,836 | - | - | |
07 | 3.4111: Use closed cycle process to minimize waste water production | $1,760 | $590 | - | - | - |
$1,760
-
Tgal
|
- | |
08 | 4.514: Re-arrange equipment layout to reduce handling costs | $426,660 | $121,000 | - | $(-234,000.0) | - | - | $660,660 | |
TOTAL RECOMMENDED | $448,178 | $184,368 |
$24,858
483,000
kWh
|
$(-234,936.0) | $(-4,164.0) |
$1,760
-
Tgal
|
$660,660 | ||
TOTAL IMPLEMENTED | $10,060 | $14,478 |
$8,300
161,195
kWh
|
- | - |
$1,760
-
Tgal
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Personnel Changes Savings | Administrative Changes Savings | Water Consumption Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs