ITAC Assessment: WV0111
ITAC logo
ITAC Assessment: WV0111
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Manganese Castings
NAICS
n/a
SIC 3369: Nonferrous Foundries, Except Aluminum and Copper
Sales Range $10
M
to 50
M
# of Employees 249
Plant Area 275,000
ft2
Annual Production 18,000
ton
Production Hrs. Annual 6,600
hrs
Location (State) Pennsylvania

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,528,702 33,201,056
kWh
Electricity Demand $221,712 36,952
kW-mo/yr
Electricity Fees $(-104,300.0) -
Natural Gas $483,507 86,669
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $166,700 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $60,393

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings By-product Production Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $338 $96 $68
1,465
kWh
$270
-
kW-mo/yr
- - -
02 2.4133: Use most efficient type of electric motors $7,354 $27,486 $3,238
75,322
kWh
$4,116
-
kW-mo/yr
- - -
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $4,858 $720 $4,858
113,130
kWh
- - - -
04 2.4231: Reduce the pressure of compressed air to the minimum required $9,405 $250 $9,405
219,226
kWh
- - - -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,373 $100 $2,373
55,393
kWh
- - - -
06 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary $42,260 - $42,260
985,346
kWh
- - - -
07 2.5114: Use shaft type furnaces for preheating incoming material $38,225 $20,000 $38,225
1,611,958
kWh
- - - -
08 2.3412: Use waste heat to produce steam to drive a steam turbine-generator $58,339 $56,250 $39,055
910,609
kWh
$25,284
-
kW-mo/yr
- $(-6,000.0) -
09 2.1311: Replace electrically-operated equipment with fossil fuel equipment $1,033 $2,000 $1,853
43,083
kWh
- $(-820.0)
-
MMBtu
- -
10 3.5217: Reuse / recycle/ sell paper products $1,079 - - - - - $1,079
11 3.5315: Lease / purchase baler; sell cardboard to recycler $180 - - - - - $180
12 2.6224: Schedule baking times of small and large components $1,256 $2,400 $1,256
65,944
kWh
- - - -
TOTAL RECOMMENDED $166,700 $109,302 $142,591
4,081,476
kWh
$29,670
-
kW-mo/yr
$(-820.0)
-
MMBtu
$(-6,000.0) $1,259
TOTAL IMPLEMENTED $60,393 $32,706 $55,838
1,338,218
kWh
$4,116
-
kW-mo/yr
$(-820.0)
-
MMBtu
- $1,259
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings By-product Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs