ITAC Assessment: WV0088
ITAC logo
ITAC Assessment: WV0088
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Steel Strappings
NAICS
n/a
SIC 3499: Fabricated Metal Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 75
Plant Area 117,000
ft2
Annual Production 69,287,400
lb
Production Hrs. Annual 5,880
hrs
Location (State) West Virginia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $306,285 12,439,332
kWh
Electricity Demand $247,821 32,260
kW-mo/yr
Electricity Fees $28,220 -
Natural Gas $130,877 53,412
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $30,093 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $4,629

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Other Liquid (non-haz) Savings Administrative Changes Savings
01 2.7241: Install outside air damper / economizer on hvac unit $1,698 $4,800 $1,698
127,198
kWh
- - - - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $1,333 $1,450 $549
23,154
kWh
$784
-
kW-mo/yr
- - - -
03 2.4133: Use most efficient type of electric motors $354 $365 $70
2,931
kWh
$284
-
kW-mo/yr
- - - -
04 2.3412: Use waste heat to produce steam to drive a steam turbine-generator $22,916 $56,250 $15,334
650,351
kWh
$10,582
-
kW-mo/yr
- - - $(-3,000.0)
05 2.4111: Utilize energy-efficient belts and other improved mechanisms $208 $680 $208
8,792
kWh
- - - - -
06 2.2437: Recover waste heat from equipment $610 $747 - - $610
-
MMBtu
- - -
07 2.2511: Insulate bare equipment $2,734 $252 $1,586
67,116
kWh
$1,148
-
kW-mo/yr
- - - -
08 3.4111: Use closed cycle process to minimize waste water production $240 $1,000 - - - $800
-
Tgal
$(-400.0)
-
gal
$(-160.0)
TOTAL RECOMMENDED $30,093 $65,544 $19,445
879,542
kWh
$12,798
-
kW-mo/yr
$610
-
MMBtu
$800
-
Tgal
$(-400.0)
-
gal
$(-3,160.0)
TOTAL IMPLEMENTED $4,629 $2,747 $2,413
101,993
kWh
$2,216
-
kW-mo/yr
- - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Other Liquid (non-haz) Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs