Assessment Year | 1996 |
---|---|
Principal Product | Boiler tubular panels |
NAICS |
n/a
|
SIC | 3443: Fabricated Plate Work (Boiler Shops) |
Sales Range | $10 M to 50M |
# of Employees | 45 |
Plant Area |
180,000
ft2
|
Annual Production | 2,500
ton
|
Production Hrs. Annual | 4,160
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $35,378 | 925,264 |
kWh
|
$0.038 |
Electricity Demand | $64,168 | 3,495 |
kW-mo/yr
|
$18.36 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $20,865 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $11,685 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $962 | $6,073 |
$962
22,274
kWh
|
- | - | |
02 | 2.4133: Use most efficient type of electric motors | $779 | $3,050 |
$779
18,171
kWh
|
- | - | |
03 | 2.4314: Use synthetic lubricant | $250 | $400 |
$250
5,569
kWh
|
- | - | |
04 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $9,694 | $500 | - |
$9,694
-
kW-mo/yr
|
- | |
05 | 3.4111: Use closed cycle process to minimize waste water production | $9,180 | $9,200 |
$(-420.0)
(-9,672)
kWh
|
- |
$9,600
-
Tgal
|
|
TOTAL RECOMMENDED | $20,865 | $19,223 |
$1,571
36,342
kWh
|
$9,694
-
kW-mo/yr
|
$9,600
-
Tgal
|
||
TOTAL IMPLEMENTED | $11,685 | $10,023 |
$1,991
46,014
kWh
|
$9,694
-
kW-mo/yr
|
- |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs