ITAC Assessment: CI0036
ITAC logo
ITAC Assessment: CI0036
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product Lead Acid Batteries
NAICS 335911: Storage Battery Manufacturing
SIC 3691: Storage Batteries
Sales Range $100
M
to 500
M
# of Employees 175
Plant Area 39,130
ft2
Annual Production 1,600,000
pieces
Production Hrs. Annual 6,912
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,224,576 8,356,868
kWh
Electricity Demand $395,117 15,802
kW-mo/yr
Electricity Fees $(-10,190.0) -
Natural Gas $761,522 115,157
MMBtu
Waste Disposal Costs
Water Usage $20,435 3,104
Tgal
TOTAL YEARLY COSTS $2,391,460
RECOMMENDED SAVINGS* $809,472 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $400,041 $153,000 $308,216
2,103,863
kWh
$91,825
-
kW-mo/yr
-
02 2.1321: Replace fossil fuel equipment with electrical equipment $209,556 $50,000 $(-18,986.0)
(-129,600)
kWh
- $228,542
-
MMBtu
03 2.9114: Use solar heat to make electricty $101,553 $493,100 $80,553
549,850
kWh
$21,000
-
kW-mo/yr
-
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $54,033 $1,200 $42,658
291,179
kWh
$11,375
-
kW-mo/yr
-
05 2.2437: Recover waste heat from equipment $36,628 $24,000 - - $36,628
-
MMBtu
06 2.3132: Recharge batteries on during off-peak demand periods $6,300 $80 - $6,300
-
kW-mo/yr
-
07 2.1321: Replace fossil fuel equipment with electrical equipment $1,361 $8,000 $(-1,367.0)
(-9,331)
kWh
- $2,728
-
MMBtu
TOTAL RECOMMENDED $809,472 $729,380 $411,074
2,805,961
kWh
$130,500
-
kW-mo/yr
$267,898
-
MMBtu
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs