ITAC Assessment: WV0066
ITAC logo
ITAC Assessment: WV0066
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1995
Principal Product Drawer slides
NAICS
n/a
SIC 3479: Coating, Engraving, and Allied Services, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 40
Plant Area 78,000
ft2
Annual Production 4,261,000
pieces
Production Hrs. Annual 2,125
hrs
Location (State) Pennsylvania

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $86,852 954,865
kWh
Natural Gas $46,870 6,308
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $16,659 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $10,610

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.1233: Analyze flue gas for proper air/fuel ratio $10,127 $5,000 - $10,127
-
MMBtu
02 2.2437: Recover waste heat from equipment $1,755 $940 $1,755
48,945
kWh
-
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $483 - $483
13,482
kWh
-
04 2.1213: Direct warmest air to combustion intake $4,294 $7,445 - $4,294
-
MMBtu
TOTAL RECOMMENDED $16,659 $13,385 $2,238
62,427
kWh
$14,421
-
MMBtu
TOTAL IMPLEMENTED $10,610 $5,000 $483
13,482
kWh
$10,127
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs