Assessment Year | 1995 |
---|---|
Principal Product | Automotive Textiles |
NAICS |
n/a
|
SIC | 2273: Carpets and Rugs |
Sales Range | $10 M to 50M |
# of Employees | 162 |
Plant Area |
80,000
ft2
|
Annual Production | 10,000,000
lb
|
Production Hrs. Annual | 7,344
hrs
|
Location (State) | West Virginia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $267,152 | 5,737,691 |
kWh
|
$0.047 |
Natural Gas | $116,099 | 17,617 |
MMBtu
|
$6.59 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $285,351 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $285,351 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,021 | - |
$1,021
33,998
kWh
|
- | - | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,161 | $500 |
$2,161
71,805
kWh
|
- | - | - | |
03 | 2.2437: Recover waste heat from equipment | $2,306 | $690 | - |
$2,306
-
MMBtu
|
- | - | |
04 | 2.1233: Analyze flue gas for proper air/fuel ratio | $10,787 | $1,000 | - |
$10,787
-
MMBtu
|
- | - | |
05 | 2.4314: Use synthetic lubricant | $988 | - |
$988
32,825
kWh
|
- | - | - | |
06 | 2.6127: Maintain air filters by cleaning or replacement | $23,617 | $15,458 |
$2,542
84,408
kWh
|
$21,075
-
MMBtu
|
- | - | |
07 | 3.1192: Reduce scrap production | $244,471 | $36,720 | - |
$7,223
-
MMBtu
|
$224,855
-
lb
|
$12,393 | |
TOTAL RECOMMENDED | $285,351 | $54,368 |
$6,712
223,036
kWh
|
$41,391
-
MMBtu
|
$224,855
-
lb
|
$12,393 | ||
TOTAL IMPLEMENTED | $285,351 | $54,368 |
$6,712
223,036
kWh
|
$41,391
-
MMBtu
|
$224,855
-
lb
|
$12,393 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs