ITAC Assessment: WM0246
ITAC logo
ITAC Assessment: WM0246
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2025
Principal Product Lighting Products
NAICS 423990: Other Miscellaneous Durable Goods Merchant Wholesalers
SIC 3641: Electric Lamp Bulbs and Tubes
Sales Range $100
M
to 500
M
# of Employees 491
Plant Area 640,000
ft2
Annual Production 400,000
units
Production Hrs. Annual 2,600
hrs
Location (State) Wisconsin

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $545,980 7,715,654
kWh
Electricity Demand $353,404 19,207
kW-mo/yr
Electricity Fees $96,538 -
Natural Gas $72,469 43,119
MMBtu
TOTAL YEARLY COSTS $1,068,391
RECOMMENDED SAVINGS* $20,195 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.4231: Reduce the pressure of compressed air to the minimum required $12,702 - $5,784
81,463
kWh
$6,918
-
kW-mo/yr
02 2.3132: Recharge batteries on during off-peak demand periods $6,226 - $6,226
183,108
kWh
-
03 2.7142: Utilize higher efficiency lamps and/or ballasts $1,267 $1,081 $659
9,287
kWh
$607
-
kW-mo/yr
TOTAL RECOMMENDED $20,195 $1,081 $12,669
273,858
kWh
$7,526
-
kW-mo/yr
TOTAL IMPLEMENTED - - - -