| Assessment Year | 2024 |
|---|---|
| Principal Product | wastewater |
| NAICS | 221320: Sewage Treatment Facilities |
| SIC | 4952: Sewerage Systems |
| Sales Range | less than $500 k |
| # of Employees | 4 |
| Plant Area |
44,888
ft2
|
| Annual Production | 2,920,000
Tgal
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Wisconsin |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $364,198 | 7,193,879 |
kWh
|
$0.051 | |
| Electricity Demand | $176,323 | 12,925 |
kW-mo/yr
|
$13.64 | |
| Electricity Fees | $38,373 | - |
|
- | |
| Natural Gas | $56,257 | 6,140 |
MMBtu
|
$9.16 | |
| Waste Disposal Costs | |||||
| Water Usage | $7,053 | 530 |
Tgal
|
$13.31 | |
| TOTAL YEARLY COSTS | $642,204 | ||||
| RECOMMENDED SAVINGS* | $14,800 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7231: Use radiant heater for spot heating | $9,218 | $9,231 | - | - |
$9,218
-
MMBtu
|
|
| 02 | 2.7224: Reduce space conditioning during non-working hours | $2,160 | - |
$2,160
42,336
kWh
|
- | - | |
| 03 | 2.7444: Close holes and openings in building such as broken windows | $1,253 | $882 | - | - |
$1,253
-
MMBtu
|
|
| 04 | 2.7221: Lower temperature during the winter season and vice-versa | $1,029 | - |
$367
7,191
kWh
|
$134
-
kW-mo/yr
|
$529
-
MMBtu
|
|
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $564 | $632 |
$306
6,001
kWh
|
$258
-
kW-mo/yr
|
- | |
| 06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $320 | $180 |
$235
4,600
kWh
|
$86
-
kW-mo/yr
|
- | |
| 07 | 2.7135: Install occupancy sensors | $255 | $480 |
$138
2,711
kWh
|
$117
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $14,800 | $11,405 |
$3,206
62,839
kWh
|
$595
-
kW-mo/yr
|
$11,000
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs