| Assessment Year | 2024 |
|---|---|
| Principal Product | Aircraft wheels and brakes |
| NAICS | 336413: Other Aircraft Parts and Auxiliary Equipment Manufacturing |
| SIC | 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 50 |
| Plant Area |
30,000
ft2
|
| Annual Production | 11,000
units
|
| Production Hrs. Annual | 2,550
hrs
|
| Location (State) | Wisconsin |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $57,806 | 668,341 |
kWh
|
$0.086 | |
| Electricity Demand | $38,347 | 2,216 |
kW-mo/yr
|
$17.30 | |
| Electricity Fees | $9,594 | - |
|
- | |
| Natural Gas | $16,060 | 1,669 |
MMBtu
|
$9.62 | |
| Waste Disposal Costs | |||||
| Water Usage | $1,101 | 269 |
Tgal
|
$4.09 | |
| Water Disposal | $1,476 | 269 |
Tgal
|
$5.49 | |
| TOTAL YEARLY COSTS | $124,384 | ||||
| RECOMMENDED SAVINGS* | $3,984 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $2,859 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7221: Lower temperature during the winter season and vice-versa | $1,593 | - |
$787
9,146
kWh
|
$215
-
kW-mo/yr
|
$591
-
MMBtu
|
|
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $886 | $2,650 |
$403
4,686
kWh
|
$483
-
kW-mo/yr
|
- | |
| 03 | 2.4221: Install compressor air intakes in coolest locations | $698 | $1,730 |
$318
3,692
kWh
|
$381
-
kW-mo/yr
|
- | |
| 04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $568 | - |
$259
3,006
kWh
|
$310
-
kW-mo/yr
|
- | |
| 05 | 2.4227: Use compressor air filters | $239 | $573 |
$109
1,263
kWh
|
$130
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $3,984 | $4,953 |
$1,874
21,793
kWh
|
$1,519
-
kW-mo/yr
|
$591
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $2,859 | $1,730 |
$1,363
15,844
kWh
|
$906
-
kW-mo/yr
|
$591
-
MMBtu
|
||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs