ITAC Assessment: WM0209
ITAC logo
ITAC Assessment: WM0209
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product Plastic manufacturer
NAICS 326199: All Other Plastics Product Manufacturing
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 74
Plant Area 55,000
ft2
Annual Production 348,333,628
lb
Production Hrs. Annual 8,760
hrs
Location (State) Wisconsin

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $554,859 9,381,600
kWh
Electricity Demand $139,202 15,448
kW-mo/yr
Electricity Fees $272,823 -
Natural Gas $27,722 3,325
MMBtu
Waste Disposal Costs
Water Usage $2,436 199
Tgal
TOTAL YEARLY COSTS $997,042
RECOMMENDED SAVINGS* $26,970 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $21,374

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings
01 4.821: Pay bills on time to avoid late fees $9,737 - - - $9,737
02 2.4322: Use or replace with energy efficient substitutes $7,576 $1,700 $2,746
46,538
kWh
$4,830
-
kW-mo/yr
-
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $4,061 $3,250 $3,358
56,921
kWh
$703
-
kW-mo/yr
-
04 2.4231: Reduce the pressure of compressed air to the minimum required $4,372 - $3,615
61,265
kWh
$757
-
kW-mo/yr
-
05 2.7221: Lower temperature during the winter season and vice-versa $1,224 - $999
16,932
kWh
$225
-
kW-mo/yr
-
TOTAL RECOMMENDED $26,970 $4,950 $10,718
181,656
kWh
$6,515
-
kW-mo/yr
$9,737
TOTAL IMPLEMENTED $21,374 $4,950 $6,104
103,459
kWh
$5,533
-
kW-mo/yr
$9,737
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs