Assessment Year | 2011 |
---|---|
Principal Product | wire and cable |
NAICS | 334417: Electronic Connector Manufacturing |
SIC | 3678: Electronic Connectors |
Sales Range | $10 M to 50M |
# of Employees | 260 |
Plant Area |
136,000
ft2
|
Annual Production | 0
units
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $780,230 | 8,412,643 |
kWh
|
$0.093 |
Electricity Demand | $102,866 | 15,660 |
kW-mo/yr
|
$6.57 |
Electricity Fees | $40,918 | - |
|
- |
Natural Gas | $80,771 | 10,093 |
MMBtu
|
$8.00 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $95,541 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $47,999 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7221: Lower temperature during the winter season and vice-versa | $12,161 | - |
$750
8,086
kWh
|
- |
$11,411
-
MMBtu
|
|
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $7,394 | - |
$7,394
79,763
kWh
|
- | - | |
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $2,482 | $1,759 |
$2,482
26,773
kWh
|
- | - | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $12,301 | $9,456 |
$11,062
119,334
kWh
|
$1,239
-
kW-mo/yr
|
- | |
05 | 2.7132: Install timers on light switches in little used areas | $2,066 | $2,420 |
$1,858
20,040
kWh
|
$208
-
kW-mo/yr
|
- | |
06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,920 | $6,639 |
$3,920
42,291
kWh
|
- | - | |
07 | 2.4133: Use most efficient type of electric motors | $3,428 | $6,271 |
$3,428
31,224
kWh
|
- | - | |
08 | 2.7135: Install occupancy sensors | $3,294 | $7,163 |
$2,410
26,000
kWh
|
$884
-
kW-mo/yr
|
- | |
09 | 2.6218: Turn off equipment when not in use | $19,656 | $79,881 |
$19,656
212,037
kWh
|
- | - | |
10 | 2.4131: Size electric motors for peak operating efficiency | $28,839 | $152,713 |
$28,839
311,108
kWh
|
- | - | |
TOTAL RECOMMENDED | $95,541 | $266,302 |
$81,799
876,656
kWh
|
$2,331
-
kW-mo/yr
|
$11,411
-
MMBtu
|
||
TOTAL IMPLEMENTED | $47,999 | $95,735 |
$35,496
377,150
kWh
|
$1,092
-
kW-mo/yr
|
$11,411
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs