| Assessment Year | 2002 |
|---|---|
| Principal Product | one quart plastic oil bottles |
| NAICS |
n/a
|
| SIC | 3085: Plastics Bottles |
| Sales Range | $10 M to 50M |
| # of Employees | 50 |
| Plant Area |
127,000
ft2
|
| Annual Production | 136,000,000
pieces
|
| Production Hrs. Annual | 5,928
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $832,464 | 9,073,943 |
kWh
|
$0.092 |
| Electricity Demand | $274,933 | 20,496 |
kW-mo/yr
|
$13.41 |
| Electricity Fees | $43,827 | - |
|
- |
| Natural Gas | $24,093 | 3,714 |
MMBtu
|
$6.49 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $115,923 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $107,048 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Increase in Production Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4239: Eliminate or reduce compressed air usage | $4,509 | - |
$3,488
37,766
kWh
|
$1,021
-
kW-mo/yr
|
- | - | - | |
| 02 | 2.7145: Install skylights | $5,597 | $10,400 |
$4,978
41,612
kWh
|
$619
-
kW-mo/yr
|
- | - | - | |
| 03 | 2.4221: Install compressor air intakes in coolest locations | $3,278 | $576 |
$2,505
27,117
kWh
|
$773
-
kW-mo/yr
|
- | - | - | |
| 04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $306 | $160 |
$133
1,431
kWh
|
$173
-
kW-mo/yr
|
- | - | - | |
| 05 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $1,275 | $2,572 | - | - |
$1,275
-
lb
|
- | - | |
| 06 | 4.652: Replace existing equipment with more suitable substitutes | $78,909 | $130,043 | - | - | - | - | $78,909 | |
| 07 | 4.431: Train operators for maximum operating efficiency | $22,049 | $60,000 | - | - | - | $22,049 | - | |
| TOTAL RECOMMENDED | $115,923 | $203,751 |
$11,104
107,926
kWh
|
$2,586
-
kW-mo/yr
|
$1,275
-
lb
|
$22,049 | $78,909 | ||
| TOTAL IMPLEMENTED | $107,048 | $192,775 |
$3,621
39,197
kWh
|
$1,194
-
kW-mo/yr
|
$1,275
-
lb
|
$22,049 | $78,909 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Increase in Production Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs