ITAC Assessment: WM0206
ITAC logo
ITAC Assessment: WM0206
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product Electrical distribution equipment (switchgear)
NAICS 335311: Power, Distribution, and Specialty Transformer Manufacturing
SIC 3612: Power, Distribution, and Specialty Transformers
Sales Range $10
M
to 50
M
# of Employees 77
Plant Area 65,000
ft2
Annual Production 928
units
Production Hrs. Annual 5,000
hrs
Location (State) Wisconsin

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $26,014 527,160
kWh
Electricity Demand $24,714 2,060
kW-mo/yr
Electricity Fees $12,902 -
Natural Gas $30,856 3,706
MMBtu
LPG $10,778 43
MMBtu
Waste Disposal Costs
Water Usage $1,330 199
Tgal
Water Disposal $1,546 199
Tgal
TOTAL YEARLY COSTS $108,140
RECOMMENDED SAVINGS* $3,762 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.7231: Use radiant heater for spot heating $1,637 $6,780 - - $1,637
-
MMBtu
02 2.7135: Install occupancy sensors $1,568 $787 $1,079
22,028
kWh
$488
-
kW-mo/yr
-
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $297 $125 $222
4,540
kWh
$74
-
kW-mo/yr
-
04 2.4231: Reduce the pressure of compressed air to the minimum required $261 - $195
3,982
kWh
$66
-
kW-mo/yr
-
TOTAL RECOMMENDED $3,762 $7,692 $1,497
30,550
kWh
$629
-
kW-mo/yr
$1,637
-
MMBtu
TOTAL IMPLEMENTED - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs