| Assessment Year | 2023 |
|---|---|
| Principal Product | Ready Mixed Concrete |
| NAICS | 327320: Ready-Mix Concrete Manufacturing |
| SIC | 3273: Ready-Mixed Concrete |
| Sales Range | $5 M to 10M |
| # of Employees | 40 |
| Plant Area |
110,000
ft2
|
| Annual Production | 130,000
ton
|
| Production Hrs. Annual | 4,200
hrs
|
| Location (State) | Illinois |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $54,261 | 769,874 |
kWh
|
$0.070 | |
| Electricity Demand | $27,933 | 3,844 |
kW-mo/yr
|
$7.27 | |
| Electricity Fees | $19,000 | - |
|
- | |
| Natural Gas | $62,725 | 24,705 |
MMBtu
|
$2.54 | |
| Waste Disposal Costs | |||||
| Water Usage | $45,747 | 8,309 |
Tgal
|
$5.51 | |
| Water Disposal | $45,747 | 8,309 |
Tgal
|
$5.51 | |
| TOTAL YEARLY COSTS | $255,413 | ||||
| RECOMMENDED SAVINGS* | $25,634 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $2,108 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings |
|---|---|---|---|---|---|---|---|
| 01 | 3.4116: Meter recycled water (to reduce sewer charges) | $22,875 | $1,950 | - | - |
$22,875
-
Tgal
|
|
| 02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,440 | $2,330 |
$1,261
18,012
kWh
|
$179
-
kW-mo/yr
|
- | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $651 | $1,001 |
$502
7,174
kWh
|
$149
-
kW-mo/yr
|
- | |
| 04 | 2.7135: Install occupancy sensors | $571 | $750 |
$440
6,290
kWh
|
$131
-
kW-mo/yr
|
- | |
| 05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $97 | $240 |
$87
1,245
kWh
|
$9
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $25,634 | $6,271 |
$2,290
32,721
kWh
|
$469
-
kW-mo/yr
|
$22,875
-
Tgal
|
||
| TOTAL IMPLEMENTED | $2,108 | $3,320 |
$1,788
25,547
kWh
|
$320
-
kW-mo/yr
|
- | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs