ITAC Assessment: WM0191
ITAC logo
ITAC Assessment: WM0191
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product Wastewater Treatment Plant
NAICS 221320: Sewage Treatment Facilities
SIC 4952: Sewerage Systems
Sales Range less than $500
k
# of Employees 25
Plant Area 1,672,000
ft2
Annual Production 15,500
Tgal
Production Hrs. Annual 8,760
hrs
Location (State) Wisconsin

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $652,343 10,872,383
kWh
Electricity Demand $266,041 17,349
kW-mo/yr
Natural Gas $20,105 2,446
MMBtu
Waste Disposal Costs
Water Usage $81,985 72,275
Tgal
TOTAL YEARLY COSTS $1,020,474
RECOMMENDED SAVINGS* $47,064 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $19,450

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.9114: Use solar heat to make electricty $25,222 $237,351 $25,222
420,368
kWh
- -
02 2.1311: Replace electrically-operated equipment with fossil fuel equipment $16,731 $32,670 $22,652
377,546
kWh
$6,195
-
kW-mo/yr
$(-12,116.0)
-
MMBtu
03 2.2449: Recover heat from exhausted steam, hot air or hot water $2,392 $5,000 - - $2,392
-
MMBtu
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,985 $2,600 $1,470
24,506
kWh
$515
-
kW-mo/yr
-
05 2.4231: Reduce the pressure of compressed air to the minimum required $733 - $549
9,149
kWh
$184
-
kW-mo/yr
-
TOTAL RECOMMENDED $47,064 $277,621 $49,893
831,569
kWh
$6,895
-
kW-mo/yr
$(-9,724.0)
-
MMBtu
TOTAL IMPLEMENTED $19,450 $35,270 $24,671
411,201
kWh
$6,895
-
kW-mo/yr
$(-12,116.0)
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs