| Assessment Year | 2023 |
|---|---|
| Principal Product | Wastewater Treatment Plant |
| NAICS | 221320: Sewage Treatment Facilities |
| SIC | 4952: Sewerage Systems |
| Sales Range | less than $500 k |
| # of Employees | 25 |
| Plant Area |
1,672,000
ft2
|
| Annual Production | 15,500
Tgal
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Wisconsin |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $652,343 | 10,872,383 |
kWh
|
$0.060 | |
| Electricity Demand | $266,041 | 17,349 |
kW-mo/yr
|
$15.33 | |
| Natural Gas | $20,105 | 2,446 |
MMBtu
|
$8.22 | |
| Waste Disposal Costs | |||||
| Water Usage | $81,985 | 72,275 |
Tgal
|
$1.13 | |
| TOTAL YEARLY COSTS | $1,020,474 | ||||
| RECOMMENDED SAVINGS* | $47,064 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $19,450 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.9114: Use solar heat to make electricty | $25,222 | $237,351 |
$25,222
420,368
kWh
|
- | - | |
| 02 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $16,731 | $32,670 |
$22,652
377,546
kWh
|
$6,195
-
kW-mo/yr
|
$(-12,116.0)
-
MMBtu
|
|
| 03 | 2.2449: Recover heat from exhausted steam, hot air or hot water | $2,392 | $5,000 | - | - |
$2,392
-
MMBtu
|
|
| 04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,985 | $2,600 |
$1,470
24,506
kWh
|
$515
-
kW-mo/yr
|
- | |
| 05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $733 | - |
$549
9,149
kWh
|
$184
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $47,064 | $277,621 |
$49,893
831,569
kWh
|
$6,895
-
kW-mo/yr
|
$(-9,724.0)
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $19,450 | $35,270 |
$24,671
411,201
kWh
|
$6,895
-
kW-mo/yr
|
$(-12,116.0)
-
MMBtu
|
||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs