Assessment Year | 2017 |
---|---|
Principal Product | Treat Wastewater |
NAICS | 221320: Sewage Treatment Facilities |
SIC | 4952: Sewerage Systems |
Sales Range | $1 M to 5M |
# of Employees | 10 |
Plant Area |
47,810
ft2
|
Annual Production | 80,001
units
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Wisconsin |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $150,723 | 2,508,775 |
kWh
|
$0.060 | |
Electricity Demand | $39,107 | 4,650 |
kW-mo/yr
|
$8.41 | |
Electricity Fees | $28,238 | - |
|
- | |
Natural Gas | $18,845 | 2,901 |
MMBtu
|
$6.50 | |
Waste Disposal Costs | |||||
Water Usage | $933 | 13,350 |
Tgal
|
$0.070 | |
TOTAL YEARLY COSTS | $237,846 | ||||
RECOMMENDED SAVINGS* | $105,950 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $11,432 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat | $68,853 | $480,000 |
$64,386
1,071,671
kWh
|
- |
$4,467
-
MMBtu
|
|
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $12,721 | $49,500 |
$12,721
165,432
kWh
|
- | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $10,613 | $11,130 |
$10,613
146,785
kWh
|
- | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,352 | $3,278 |
$4,352
52,749
kWh
|
- | - | |
05 | 2.7221: Lower temperature during the winter season and vice-versa | $2,204 | - | - | - |
$2,204
-
MMBtu
|
|
06 | 2.4314: Use synthetic lubricant | $1,915 | $11,475 |
$1,915
22,137
kWh
|
- | - | |
07 | 2.2211: Use optimum temperature | $1,605 | - |
$535
8,902
kWh
|
$1,070
-
kW-mo/yr
|
- | |
08 | 2.7231: Use radiant heater for spot heating | $2,133 | $3,818 | - | - |
$2,133
-
MMBtu
|
|
09 | 2.7135: Install occupancy sensors | $1,138 | $600 |
$1,138
15,651
kWh
|
- | - | |
10 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $416 | $800 |
$87
1,456
kWh
|
$329
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $105,950 | $560,601 |
$95,747
1,484,783
kWh
|
$1,398
-
kW-mo/yr
|
$8,804
-
MMBtu
|
||
TOTAL IMPLEMENTED | $11,432 | $7,696 |
$6,025
77,302
kWh
|
$1,070
-
kW-mo/yr
|
$4,337
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs