Assessment Year | 2016 |
---|---|
Principal Product | Digital Printing |
NAICS | 323117: Books Printing |
SIC | 2732: Book Printing |
Sales Range | $50 M to 100M |
# of Employees | 180 |
Plant Area |
360,000
ft2
|
Annual Production | 1,000,000
units
|
Production Hrs. Annual | 6,120
hrs
|
Location (State) | Wisconsin |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $450,841 | 5,999,969 |
kWh
|
$0.075 | |
Electricity Demand | $192,978 | 15,614 |
kW-mo/yr
|
$12.36 | |
Electricity Fees | $65,149 | - |
|
- | |
Natural Gas | $38,652 | 7,329 |
MMBtu
|
$5.27 | |
Waste Disposal Costs | |||||
Water Usage | $18,534 | 6,084,511 |
Tgal
|
$0.003 | |
TOTAL YEARLY COSTS | $766,154 | ||||
RECOMMENDED SAVINGS* | $97,144 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $12,362 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|
01 | 3.2176: Increase use of automation | $76,500 | $6,500 | - | - | $76,500 | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $12,362 | $1,245 |
$9,348
124,399
kWh
|
$3,014
-
kW-mo/yr
|
- | |
03 | 2.4221: Install compressor air intakes in coolest locations | $4,717 | $1,245 |
$3,568
47,481
kWh
|
$1,149
-
kW-mo/yr
|
- | |
04 | 2.7135: Install occupancy sensors | $1,988 | $1,575 |
$1,988
27,789
kWh
|
- | - | |
05 | 2.7134: Use photocell controls | $1,577 | $1,120 |
$959
12,768
kWh
|
$618
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $97,144 | $11,685 |
$15,863
212,437
kWh
|
$4,781
-
kW-mo/yr
|
$76,500 | ||
TOTAL IMPLEMENTED | $12,362 | $1,245 |
$9,348
124,399
kWh
|
$3,014
-
kW-mo/yr
|
- |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs