ITAC Assessment: WM0085
ITAC logo
ITAC Assessment: WM0085
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2016
Principal Product Commercial Printer
NAICS 323113: Commercial Screen Printing
SIC 2759: Commercial Printing, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 42
Plant Area 43,000
ft2
Annual Production 1,000,000
lb
Production Hrs. Annual 4,080
hrs
Location (State) Wisconsin

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $58,163 772,320
kWh
Electricity Demand $33,889 3,759
kW-mo/yr
Electricity Fees $12,478 -
Natural Gas $10,559 1,574
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $11,814 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $696

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Water Disposal Savings
01 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $6,524 $28,800 $6,524
86,625
kWh
- -
02 3.4111: Use closed cycle process to minimize waste water production $3,682 $2,500 - - $3,682
-
Tgal
03 2.7142: Utilize higher efficiency lamps and/or ballasts $912 $1,520 $886
11,771
kWh
$26
-
kW-mo/yr
-
04 2.2135: Repair and eliminate steam leaks $696 $180 $515
6,835
kWh
$181
-
kW-mo/yr
-
TOTAL RECOMMENDED $11,814 $33,000 $7,925
105,231
kWh
$207
-
kW-mo/yr
$3,682
-
Tgal
TOTAL IMPLEMENTED $696 $180 $515
6,835
kWh
$181
-
kW-mo/yr
-
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs