Assessment Year | 2016 |
---|---|
Principal Product | Drain tile, custom blow molding |
NAICS | 326122: Plastics Pipe and Pipe Fitting Manufacturing |
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 25 |
Plant Area |
50,000
ft2
|
Annual Production | 2,000,000
pieces
|
Production Hrs. Annual | 6,500
hrs
|
Location (State) | Wisconsin |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $165,351 | 2,782,789 |
kWh
|
$0.059 |
Electricity Demand | $51,253 | 7,192 |
kW-mo/yr
|
$7.13 |
Electricity Fees | $32,053 | - |
|
- |
Natural Gas | $10,392 | 1,391 |
MMBtu
|
$7.47 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $21,163 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $5,723 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.4314: Use synthetic lubricant | $4,146 | $4,500 |
$3,366
56,642
kWh
|
$780
-
kW-mo/yr
|
- | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,385 | $1,225 |
$3,385
56,977
kWh
|
- | - | |
03 | 2.4314: Use synthetic lubricant | $3,352 | $1,507 |
$2,483
41,785
kWh
|
$869
-
kW-mo/yr
|
- | |
04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $3,109 | $780 |
$2,524
42,481
kWh
|
$585
-
kW-mo/yr
|
- | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,338 | - |
$1,953
32,872
kWh
|
$385
-
kW-mo/yr
|
- | |
06 | 2.7111: Reduce illumination to minimum necessary levels | $2,275 | $1,589 |
$1,840
30,968
kWh
|
$435
-
kW-mo/yr
|
- | |
07 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $2,246 | $1,600 |
$2,246
37,791
kWh
|
- | - | |
08 | 2.2136: Install / repair insulation on steam lines | $312 | $122 | - | - |
$312
-
MMBtu
|
|
TOTAL RECOMMENDED | $21,163 | $11,323 |
$17,797
299,516
kWh
|
$3,054
-
kW-mo/yr
|
$312
-
MMBtu
|
||
TOTAL IMPLEMENTED | $5,723 | $1,225 |
$5,338
89,849
kWh
|
$385
-
kW-mo/yr
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs