ITAC Assessment: WM0080
ITAC logo
ITAC Assessment: WM0080
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2016
Principal Product Drain tile, custom blow molding
NAICS 326122: Plastics Pipe and Pipe Fitting Manufacturing
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 25
Plant Area 50,000
ft2
Annual Production 2,000,000
pieces
Production Hrs. Annual 6,500
hrs
Location (State) Wisconsin

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $165,351 2,782,789
kWh
Electricity Demand $51,253 7,192
kW-mo/yr
Electricity Fees $32,053 -
Natural Gas $10,392 1,391
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $21,163 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $5,723

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.4314: Use synthetic lubricant $4,146 $4,500 $3,366
56,642
kWh
$780
-
kW-mo/yr
-
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,385 $1,225 $3,385
56,977
kWh
- -
03 2.4314: Use synthetic lubricant $3,352 $1,507 $2,483
41,785
kWh
$869
-
kW-mo/yr
-
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $3,109 $780 $2,524
42,481
kWh
$585
-
kW-mo/yr
-
05 2.4231: Reduce the pressure of compressed air to the minimum required $2,338 - $1,953
32,872
kWh
$385
-
kW-mo/yr
-
06 2.7111: Reduce illumination to minimum necessary levels $2,275 $1,589 $1,840
30,968
kWh
$435
-
kW-mo/yr
-
07 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $2,246 $1,600 $2,246
37,791
kWh
- -
08 2.2136: Install / repair insulation on steam lines $312 $122 - - $312
-
MMBtu
TOTAL RECOMMENDED $21,163 $11,323 $17,797
299,516
kWh
$3,054
-
kW-mo/yr
$312
-
MMBtu
TOTAL IMPLEMENTED $5,723 $1,225 $5,338
89,849
kWh
$385
-
kW-mo/yr
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs