ITAC Assessment: WM0072
ITAC logo
ITAC Assessment: WM0072
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2015
Principal Product Stone veneer
NAICS 212311: Dimension Stone Mining and Quarrying
SIC 1411: Dimension Stone
Sales Range $10
M
to 50
M
# of Employees 130
Plant Area 65,000
ft2
Annual Production 110,000
ton
Production Hrs. Annual 4,590
hrs
Location (State) Wisconsin

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $153,043 2,283,535
kWh
Electricity Demand $55,065 5,953
kW-mo/yr
LPG $100,170 10,642
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $17,368 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $6,380

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings LPG Savings One-time Revenue or Avoided Cost Savings
01 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $9,713 $20,000 $7,137
106,529
kWh
$2,576
-
kW-mo/yr
- -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $2,865 $3,846 $1,981
29,564
kWh
$677
-
kW-mo/yr
- $207
03 2.7142: Utilize higher efficiency lamps and/or ballasts $2,288 $6,900 $1,893
45,384
kWh
- - $395
04 2.7135: Install occupancy sensors $1,227 $575 $1,227
18,309
kWh
- - -
05 2.2437: Recover waste heat from equipment $1,054 $1,390 - - $1,054
-
MMBtu
-
06 2.7135: Install occupancy sensors $221 $476 $221
3,299
kWh
- - -
TOTAL RECOMMENDED $17,368 $33,187 $12,459
203,085
kWh
$3,253
-
kW-mo/yr
$1,054
-
MMBtu
$602
TOTAL IMPLEMENTED $6,380 $11,321 $5,101
93,257
kWh
$677
-
kW-mo/yr
- $602
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings LPG Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs