| Assessment Year | 2013 |
|---|---|
| Principal Product | Plastic Parts |
| NAICS | 326199: All Other Plastics Product Manufacturing |
| SIC | 3089: Plastics Products, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 71 |
| Plant Area |
28,000
ft2
|
| Annual Production | 34,000,000
pieces
|
| Production Hrs. Annual | 8,232
hrs
|
| Location (State) | Wisconsin |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $194,722 | 2,984,063 |
kWh
|
$0.065 |
| Electricity Demand | $80,085 | 12,701 |
kW-mo/yr
|
$6.31 |
| Electricity Fees | $14,625 | - |
|
- |
| Natural Gas | $4,459 | 556 |
MMBtu
|
$8.03 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $29,562 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $15,628 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | By-product Production Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7124: Make a practice of turning off lights when not needed | $288 | - |
$288
4,341
kWh
|
- | - | |
| 02 | 2.7135: Install occupancy sensors | $396 | $200 |
$396
5,966
kWh
|
- | - | |
| 03 | 2.4221: Install compressor air intakes in coolest locations | $783 | $4,255 |
$632
9,515
kWh
|
$151
-
kW-mo/yr
|
- | |
| 04 | 2.2511: Insulate bare equipment | $1,540 | $5,355 |
$1,540
23,176
kWh
|
- | - | |
| 05 | 4.424: Improve space comfort conditioning | $3,641 | $595 | - | - | $3,641 | |
| 06 | 2.6242: Minimize operation of equipment maintained in standby condition | $7,574 | $780 |
$1,890
24,588
kWh
|
$5,684
-
kW-mo/yr
|
- | |
| 07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $15,340 | $1,900 |
$15,340
230,916
kWh
|
- | - | |
| TOTAL RECOMMENDED | $29,562 | $13,085 |
$20,086
298,502
kWh
|
$5,835
-
kW-mo/yr
|
$3,641 | ||
| TOTAL IMPLEMENTED | $15,628 | $1,900 |
$15,628
235,257
kWh
|
- | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | By-product Production Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs