Assessment Year | 2013 |
---|---|
Principal Product | Heavy Military Trucks and Trailers |
NAICS | 336120: Heavy Duty Truck Manufacturing |
SIC | 3711: Motor Vehicles and Passenger Car Bodies |
Sales Range | $5 M to 10M |
# of Employees | 830 |
Plant Area |
261,000
ft2
|
Annual Production | 3,385
pieces
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Wisconsin |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $421,420 | 7,893,759 |
kWh
|
$0.053 |
Electricity Demand | $232,627 | 28,409 |
kW-mo/yr
|
$8.19 |
Electricity Fees | $37,846 | - |
|
- |
Natural Gas | $298,129 | 63,943 |
MMBtu
|
$4.66 |
LPG | $64,474 | 4,488 |
MMBtu
|
$14.37 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $61,323 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $34,398 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.2437: Recover waste heat from equipment | $1,439 | $1,853 | - | - |
$1,439
-
MMBtu
|
- | |
02 | 2.7231: Use radiant heater for spot heating | $17,111 | $9,180 | - | - |
$17,111
-
MMBtu
|
- | |
03 | 2.7134: Use photocell controls | $2,234 | $4,550 |
$2,234
30,891
kWh
|
- | - | - | |
04 | 2.7111: Reduce illumination to minimum necessary levels | $1,570 | $500 |
$1,526
27,264
kWh
|
$44
-
kW-mo/yr
|
- | - | |
05 | 2.7221: Lower temperature during the winter season and vice-versa | $1,064 | - |
$1,064
14,582
kWh
|
- | - | - | |
06 | 2.7243: Improve air circulation with destratification fans / other methods | $34,398 | $69,000 | - | - |
$34,398
-
MMBtu
|
- | |
07 | 4.454: Modify startup/shutdown times | $3,034 | - | - | - | - | $3,034 | |
08 | 2.7135: Install occupancy sensors | $473 | $546 |
$473
8,080
kWh
|
- | - | - | |
TOTAL RECOMMENDED | $61,323 | $85,629 |
$5,297
80,817
kWh
|
$44
-
kW-mo/yr
|
$52,948
-
MMBtu
|
$3,034 | ||
TOTAL IMPLEMENTED | $34,398 | $69,000 | - | - |
$34,398
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs