| Assessment Year | 2013 |
|---|---|
| Principal Product | Ice cream cones and pie crust |
| NAICS | 311812: Commercial Bakeries |
| SIC | 2052: Cookies and Crackers |
| Sales Range | $100 M to 500M |
| # of Employees | 408 |
| Plant Area |
289,000
ft2
|
| Annual Production | 22
pieces
|
| Production Hrs. Annual | 6,320
hrs
|
| Location (State) | Illinois |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $517,507 | 6,904,697 |
kWh
|
$0.075 |
| Electricity Demand | $72,033 | 13,673 |
kW-mo/yr
|
$5.27 |
| Natural Gas | $425,152 | 85,102 |
MMBtu
|
$5.00 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $132,513 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $37,135 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7231: Use radiant heater for spot heating | $4,080 | $5,760 | - | - |
$4,080
-
MMBtu
|
- | - | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $8,281 | $1,625 |
$7,412
98,899
kWh
|
$868
-
kW-mo/yr
|
- | - | - | |
| 03 | 2.4314: Use synthetic lubricant | $945 | $1,200 |
$870
11,602
kWh
|
$75
-
kW-mo/yr
|
- | - | - | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $283 | $494 |
$204
2,716
kWh
|
$20
-
kW-mo/yr
|
- | - | $60 | |
| 05 | 2.7135: Install occupancy sensors | $1,427 | $630 |
$1,427
19,038
kWh
|
- | - | - | - | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $40,135 | $39,312 |
$40,135
535,496
kWh
|
- | - | - | - | |
| 07 | 4.424: Improve space comfort conditioning | $50,218 | $27,650 | - | - | - | $50,218 | - | |
| 08 | 4.424: Improve space comfort conditioning | $27,144 | $5,800 | - | - | - | - | $27,144 | |
| TOTAL RECOMMENDED | $132,513 | $82,471 |
$50,048
667,751
kWh
|
$963
-
kW-mo/yr
|
$4,080
-
MMBtu
|
$50,218 | $27,204 | ||
| TOTAL IMPLEMENTED | $37,135 | $8,549 |
$9,043
120,653
kWh
|
$888
-
kW-mo/yr
|
- | - | $27,204 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs