ITAC Assessment: WI0525
ITAC logo
ITAC Assessment: WI0525
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2006
Principal Product Bearing Caps and Clutch Plates
NAICS 332991: Ball and Roller Bearing Manufacturing
SIC 3562: Ball and Roller Bearings
Sales Range $10
M
to 50
M
# of Employees 130
Plant Area 71,000
ft2
Annual Production 18,000,000
pieces
Production Hrs. Annual 8,400
hrs
Location (State) Wisconsin

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $524,927 15,539,407
kWh
Electricity Demand $194,102 26,497
kW-mo/yr
Natural Gas $157,124 179,923
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $34,106 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $13,775 $23,040 $10,520
296,352
kWh
$3,255
-
kW-mo/yr
-
02 4.426: Modify workload $11,666 $9,000 - - $11,666
03 3.6193: Install equipment (eg compactor) to reduce disposal costs $4,600 - - - $4,600
04 2.4314: Use synthetic lubricant $3,880 - $1,770
49,867
kWh
$2,110
-
kW-mo/yr
-
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $185 $400 $185
5,211
kWh
- -
TOTAL RECOMMENDED $34,106 $32,440 $12,475
351,430
kWh
$5,365
-
kW-mo/yr
$16,266
TOTAL IMPLEMENTED - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs