ITAC Assessment: WI0491
ITAC logo
ITAC Assessment: WI0491
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2005
Principal Product Greet. Cards
NAICS 323111: Commercial Printing (except Screen and Books)
SIC 2759: Commercial Printing, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 220
Plant Area 100,000
ft2
Annual Production 18,000
ton
Production Hrs. Annual 6,000
hrs
Location (State) Wisconsin

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $129,682 4,100,580
kWh
Electricity Demand $81,391 10,437
kW-mo/yr
Natural Gas $40,932 6,430
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $47,626 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $9,729

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.7273: Install desiccant humidity control system $23,636 $25,000 $21,932
656,648
kWh
$1,704
-
kW-mo/yr
-
02 2.2621: Modify refrigeration system to operate at a lower pressure $12,939 $15,000 $7,071
211,702
kWh
$5,868
-
kW-mo/yr
-
03 2.7243: Improve air circulation with destratification fans / other methods $7,911 $5,000 - - $7,911
-
MMBtu
04 2.4312: Improve lubrication practices $1,322 $2,340 $1,108
33,160
kWh
$214
-
kW-mo/yr
-
05 2.7135: Install occupancy sensors $1,112 $1,680 $1,112
33,304
kWh
- -
06 2.4111: Utilize energy-efficient belts and other improved mechanisms $706 $1,244 $484
13,427
kWh
$222
-
kW-mo/yr
-
TOTAL RECOMMENDED $47,626 $50,264 $31,707
948,241
kWh
$8,008
-
kW-mo/yr
$7,911
-
MMBtu
TOTAL IMPLEMENTED $9,729 $7,924 $1,596
46,731
kWh
$222
-
kW-mo/yr
$7,911
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs