Assessment Year | 2004 |
---|---|
Principal Product | Vitamin Supplements |
NAICS | 325412: Pharmaceutical Preparation Manufacturing |
SIC | 2834: Pharmaceutical Preparations |
Sales Range | $50 M to 100M |
# of Employees | 230 |
Plant Area |
150,000
ft2
|
Annual Production | 0
units
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Wisconsin |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $103,869 | 3,676,760 |
kWh
|
$0.028 |
Electricity Demand | $59,891 | 8,053 |
kW-mo/yr
|
$7.44 |
Electricity Fees | $10,479 | - |
|
- |
Natural Gas | $66,773 | 10,486 |
MMBtu
|
$6.37 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $18,589 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,956 | $16,640 | n/a |
$4,556
152,880
kWh
|
$2,400
-
kW-mo/yr
|
- |
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $5,258 | $9,780 | n/a |
$5,258
176,446
kWh
|
- | - |
03 | 2.7135: Install occupancy sensors | $1,700 | $5,500 | n/a |
$1,700
57,069
kWh
|
- | - |
04 | 2.4221: Install compressor air intakes in coolest locations | $596 | $640 | n/a |
$376
12,620
kWh
|
$220
-
kW-mo/yr
|
- |
05 | 3.4111: Use closed cycle process to minimize waste water production | $1,375 | $1,145 | n/a |
$901
30,213
kWh
|
$474
-
kW-mo/yr
|
- |
06 | 2.2414: Use waste heat from hot flue gases to preheat | $1,106 | $5,500 | n/a | - | - |
$1,106
-
MMBtu
|
07 | 2.1233: Analyze flue gas for proper air/fuel ratio | $566 | $500 | n/a | - | - |
$566
-
MMBtu
|
08 | 2.3132: Recharge batteries on during off-peak demand periods | $1,032 | $700 | n/a | - |
$1,032
-
kW-mo/yr
|
- |
TOTAL RECOMMENDED | $18,589 | $40,405 |
$12,791
429,228
kWh
|
$4,126
-
kW-mo/yr
|
$1,672
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs