ITAC Assessment: WI0461
ITAC logo
ITAC Assessment: WI0461
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2004
Principal Product Wooden Pallets and Boxes
NAICS 321113: Sawmills
SIC 2421: Sawmills and Planing Mills, General
Sales Range $5
M
to 10
M
# of Employees 65
Plant Area 75,000
ft2
Annual Production 100,000
pieces
Production Hrs. Annual 2,250
hrs
Location (State) Wisconsin

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $53,702 749,382
kWh
Electricity Demand $28,433 2,740
kW-mo/yr
Electricity Fees $7,392 -
Natural Gas $29,720 52,270
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $13,709 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,032

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $6,591 $14,685 n/a $3,608
47,659
kWh
$2,983
-
kW-mo/yr
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,032 $360 $1,228
30,845
kWh
$1,804
-
kW-mo/yr
03 2.4231: Reduce the pressure of compressed air to the minimum required $475 - $192
4,834
kWh
$283
-
kW-mo/yr
04 2.4133: Use most efficient type of electric motors $1,930 $5,784 $735
18,492
kWh
$1,195
-
kW-mo/yr
05 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,681 $1,227 $699
17,581
kWh
$982
-
kW-mo/yr
TOTAL RECOMMENDED $13,709 $22,056 $6,462
119,411
kWh
$7,247
-
kW-mo/yr
TOTAL IMPLEMENTED $3,032 $360 $1,228
30,845
kWh
$1,804
-
kW-mo/yr
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs