ITAC Assessment: WI0428
ITAC logo
ITAC Assessment: WI0428
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product Compressors & V. Pumps
NAICS
n/a
SIC 3567: Industrial Process Furnaces and Ovens
Sales Range $10
M
to 50
M
# of Employees 230
Plant Area 208,000
ft2
Annual Production 0
units
Production Hrs. Annual 6,000
hrs
Location (State) Wisconsin

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $161,417 6,201,300
kWh
Electricity Demand $130,313 15,065
kW-mo/yr
Electricity Fees $47,670 -
Natural Gas $52,203 7,948
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $37,695 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $5,416

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.4231: Reduce the pressure of compressed air to the minimum required $17,872 $18,000 $6,110
223,800
kWh
$11,762
-
kW-mo/yr
-
02 2.7135: Install occupancy sensors $6,258 $2,100 $4,175
152,928
kWh
$2,083
-
kW-mo/yr
-
03 2.7224: Reduce space conditioning during non-working hours $4,612 $1,200 - - $4,612
-
MMBtu
04 2.7142: Utilize higher efficiency lamps and/or ballasts $2,687 - $1,886
69,090
kWh
$801
-
kW-mo/yr
-
05 2.7314: Reduce ventilation air $2,242 $4,100 $819
29,989
kWh
$1,423
-
kW-mo/yr
-
06 2.4133: Use most efficient type of electric motors $1,569 $1,000 $91
3,316
kWh
$1,478
-
kW-mo/yr
-
07 2.7142: Utilize higher efficiency lamps and/or ballasts $849 $4,685 $588
21,546
kWh
$261
-
kW-mo/yr
-
08 2.7124: Make a practice of turning off lights when not needed $804 $2,000 $457
16,757
kWh
$347
-
kW-mo/yr
-
09 2.4111: Utilize energy-efficient belts and other improved mechanisms $802 $616 $543
19,893
kWh
$259
-
kW-mo/yr
-
TOTAL RECOMMENDED $37,695 $33,701 $14,669
537,319
kWh
$18,414
-
kW-mo/yr
$4,612
-
MMBtu
TOTAL IMPLEMENTED $5,416 $3,200 $457
16,757
kWh
$347
-
kW-mo/yr
$4,612
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs