ITAC Assessment: WI0362
ITAC logo
ITAC Assessment: WI0362
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Hydraulic, Water, and Air Hoses
NAICS
n/a
SIC 3492: Fluid Power Valves and Hose Fittings
Sales Range $10
M
to 50
M
# of Employees 110
Plant Area 140,000
ft2
Annual Production 30,000,000
thousand feet
Production Hrs. Annual 6,000
hrs
Location (State) Wisconsin

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $214,625 7,027,550
kWh
Electricity Demand $106,689 16,546
kW-mo/yr
Electricity Fees $28,950 -
Natural Gas $44,597 13,327
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $24,436 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,598

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Water Disposal Savings Solid Waste (non-haz) Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $6,236 $1,860 $4,737
147,714
kWh
$1,499
-
kW-mo/yr
- - - -
02 2.4221: Install compressor air intakes in coolest locations $1,550 $740 $1,123
34,877
kWh
$427
-
kW-mo/yr
- - - -
03 2.3131: Reschedule plant operations or reduce load to avoid peaks $5,619 $16,000 $3,387
105,510
kWh
$2,232
-
kW-mo/yr
- - - -
04 3.4114: Replace city water with recycled water via cooling tower $3,741 $14,500 $(-384.0)
(-12,016)
kWh
$(-163.0)
-
kW-mo/yr
$4,788
-
Tgal
- $(-500.0) -
05 3.4113: Treat and reuse rinse waters $3,598 $6,375 - - $5,098
-
Tgal
- - $(-1,500.0)
06 2.4111: Utilize energy-efficient belts and other improved mechanisms $2,130 $2,150 $1,414
43,962
kWh
$716
-
kW-mo/yr
- - - -
07 3.5218: Reuse / recycle/ sell rubber products $1,562 - - - - $1,562
-
lb
- -
TOTAL RECOMMENDED $24,436 $41,625 $10,277
320,047
kWh
$4,711
-
kW-mo/yr
$9,886
-
Tgal
$1,562
-
lb
$(-500.0) $(-1,500.0)
TOTAL IMPLEMENTED $3,598 $6,375 - - $5,098
-
Tgal
- - $(-1,500.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Water Disposal Savings Solid Waste (non-haz) Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs