ITAC Assessment: WI0355
ITAC logo
ITAC Assessment: WI0355
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Commercial Printed Products
NAICS
n/a
SIC 2752: Commercial Printing, Lithographic
Sales Range $10
M
to 50
M
# of Employees 95
Plant Area 40,000
ft2
Annual Production 0
units
Production Hrs. Annual 6,000
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $53,933 1,465,416
kWh
Electricity Demand $69,776 5,628
kW-mo/yr
Electricity Fees $16,693 -
Natural Gas $15,685 3,415
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $10,770 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Personnel Changes Savings
01 2.4111: Utilize energy-efficient belts and other improved mechanisms $3,454 $1,484 n/a $2,092
53,634
kWh
$1,362
-
kW-mo/yr
- -
02 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $2,359 $7,200 n/a $2,359
60,668
kWh
- - -
03 4.445: Install equipment to move product $1,875 $6,350 n/a - - - $1,875
04 3.6192: Use a less expensive method of waste removal $1,752 - n/a - - $1,752
-
lb
-
05 2.7142: Utilize higher efficiency lamps and/or ballasts $689 $1,807 n/a $304
7,913
kWh
$385
-
kW-mo/yr
- -
06 2.4221: Install compressor air intakes in coolest locations $641 $640 n/a $384
9,965
kWh
$257
-
kW-mo/yr
- -
TOTAL RECOMMENDED $10,770 $17,481 $5,139
132,180
kWh
$2,004
-
kW-mo/yr
$1,752
-
lb
$1,875
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs