| Assessment Year | 1999 |
|---|---|
| Principal Product | Power Conditioners |
| NAICS |
n/a
|
| SIC | 3674: Semiconductors and Related Devices |
| Sales Range | $10 M to 50M |
| # of Employees | 170 |
| Plant Area |
107,120
ft2
|
| Annual Production | 1,045,000
pieces
|
| Production Hrs. Annual | 2,125
hrs
|
| Location (State) | Illinois |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $51,255 | 1,472,743 |
kWh
|
$0.035 |
| Electricity Demand | $48,768 | 3,933 |
kW-mo/yr
|
$12.40 |
| Electricity Fees | $4,764 | - |
|
- |
| Natural Gas | $15,418 | 3,781 |
MMBtu
|
$4.08 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $14,468 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $4,934 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Primary Raw Material Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.3134: Shift from daytime to nighttime operation | $3,909 | - | - |
$3,909
-
kW-mo/yr
|
- | - | - | - | - | |
| 02 | 2.3132: Recharge batteries on during off-peak demand periods | $245 | $300 | - |
$245
-
kW-mo/yr
|
- | - | - | - | - | |
| 03 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $2,824 | $1,000 | - | - | - | - |
$2,824
-
lb
|
- | - | |
| 04 | 2.7135: Install occupancy sensors | $1,826 | $2,400 |
$475
12,896
kWh
|
$1,351
-
kW-mo/yr
|
- | - | - | - | - | |
| 05 | 3.8142: Distill contaminated solvents for reuse | $2,534 | $4,000 | - | - | - |
$1,320
-
gal
|
$(-131.0)
-
lb
|
$(-264.0) | $1,609 | |
| 06 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $1,865 | $2,000 |
$883
24,033
kWh
|
$982
-
kW-mo/yr
|
- | - | - | - | - | |
| 07 | 2.7243: Improve air circulation with destratification fans / other methods | $826 | $2,600 |
$(-65.0)
(-1,758)
kWh
|
- |
$891
-
MMBtu
|
- | - | - | - | |
| 08 | 2.7261: Install timers and/or thermostats | $439 | - | - | - |
$439
-
MMBtu
|
- | - | - | - | |
| TOTAL RECOMMENDED | $14,468 | $12,300 |
$1,293
35,171
kWh
|
$6,487
-
kW-mo/yr
|
$1,330
-
MMBtu
|
$1,320
-
gal
|
$2,693
-
lb
|
$(-264.0) | $1,609 | ||
| TOTAL IMPLEMENTED | $4,934 | $3,300 |
$883
24,033
kWh
|
$1,227
-
kW-mo/yr
|
- | - |
$2,824
-
lb
|
- | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Primary Raw Material Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs