Assessment Year | 1997 |
---|---|
Principal Product | Farm Machinery |
NAICS |
n/a
|
SIC | 3523: Farm Machinery and Equipment |
Sales Range | $10 M to 50M |
# of Employees | 70 |
Plant Area |
142,250
ft2
|
Annual Production | 2,000
pieces
|
Production Hrs. Annual | 2,875
hrs
|
Location (State) | Wisconsin |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $32,600 | 808,324 |
kWh
|
$0.040 |
Electricity Demand | $19,983 | 2,290 |
kW-mo/yr
|
$8.73 |
Electricity Fees | $755 | - |
|
- |
Natural Gas | $44,223 | 8,626 |
MMBtu
|
$5.13 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $77,051 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $51,530 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Solid Waste (haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Raw Material Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 3.2123: Convert to high volume low pressure (hvlp) paint guns | $36,638 | $2,500 | - | - | - |
$4,668
-
lb
|
- | - | $31,970 | |
02 | 2.8113: Purchase gas directly from a contract gas supplier | $11,074 | $500 | - | - | - | - | - | $11,074 | - | |
03 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $11,031 | $8,700 | - | - | - |
$11,031
-
lb
|
- | - | - | |
04 | 3.6192: Use a less expensive method of waste removal | $10,950 | - | - | - | - | - | - | $10,950 | - | |
05 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $1,700 | - | - | - |
$1,700
-
lb
|
- | - | - | - | |
06 | 3.8122: Use tight-fitting lids on material containers to reduce voc emissions | $3,726 | $1,000 | - | - | - | - | $3,375 | - | $351 | |
07 | 2.8121: Apply for tax-free status for energy purchases | $1,716 | - | - | - | - | - | - | $1,716 | - | |
08 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $216 | $90 |
$129
2,931
kWh
|
$87
-
kW-mo/yr
|
- | - | - | - | - | |
TOTAL RECOMMENDED | $77,051 | $12,790 |
$129
2,931
kWh
|
$87
-
kW-mo/yr
|
$1,700
-
lb
|
$15,699
-
lb
|
$3,375 | $23,740 | $32,321 | ||
TOTAL IMPLEMENTED | $51,530 | $3,590 |
$129
2,931
kWh
|
$87
-
kW-mo/yr
|
- |
$4,668
-
lb
|
$3,375 | $10,950 | $32,321 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Solid Waste (haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Raw Material Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs