Assessment Year | 1997 |
---|---|
Principal Product | Trailer and marine accessories |
NAICS |
n/a
|
SIC | 3465: Automotive Stampings |
Sales Range | $10 M to 50M |
# of Employees | 110 |
Plant Area |
110,000
ft2
|
Annual Production | 7,150,000
pieces
|
Production Hrs. Annual | 2,125
hrs
|
Location (State) | Wisconsin |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $29,846 | 1,073,857 |
kWh
|
$0.028 |
Electricity Demand | $32,308 | 3,691 |
kW-mo/yr
|
$8.75 |
Electricity Fees | $850 | - |
|
- |
Natural Gas | $35,795 | 7,682 |
MMBtu
|
$4.66 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $80,043 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 4.445: Install equipment to move product | $71,719 | $240,000 | - | - | - | $71,719 | - | |
02 | 2.8113: Purchase gas directly from a contract gas supplier | $6,278 | $500 | - | - | - | - | $6,278 | |
03 | 2.3191: Use demand controller or load shedder | $1,236 | $5,000 | - |
$1,236
-
kW-mo/yr
|
- | - | - | |
04 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $420 | - | - | - |
$420
-
lb
|
- | - | |
05 | 2.4221: Install compressor air intakes in coolest locations | $390 | $1,280 |
$156
5,275
kWh
|
$234
-
kW-mo/yr
|
- | - | - | |
TOTAL RECOMMENDED | $80,043 | $246,780 |
$156
5,275
kWh
|
$1,470
-
kW-mo/yr
|
$420
-
lb
|
$71,719 | $6,278 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs