Assessment Year | 1997 |
---|---|
Principal Product | Aerosol Products |
NAICS |
n/a
|
SIC | 2842: Specialty Cleaning, Polishing, and Sanitation Preparations |
Sales Range | $10 M to 50M |
# of Employees | 120 |
Plant Area |
104,580
ft2
|
Annual Production | 40,000,000
pieces
|
Production Hrs. Annual | 2,125
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $72,744 | 1,691,383 |
kWh
|
$0.043 |
Electricity Demand | $83,237 | 6,812 |
kW-mo/yr
|
$12.22 |
Electricity Fees | $3,298 | - |
|
- |
Natural Gas | $85,369 | 22,560 |
MMBtu
|
$3.78 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $21,582 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $13,381 | $15,000 |
$8,725
192,556
kWh
|
$12,951
-
kW-mo/yr
|
$(-8,295.0)
-
MMBtu
|
|
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,215 | $3,484 |
$1,460
32,239
kWh
|
$1,755
-
kW-mo/yr
|
- | |
03 | 2.1233: Analyze flue gas for proper air/fuel ratio | $2,961 | $500 | - | - |
$2,961
-
MMBtu
|
|
04 | 2.4221: Install compressor air intakes in coolest locations | $1,329 | $840 |
$570
12,603
kWh
|
$759
-
kW-mo/yr
|
- | |
05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $696 | - |
$308
6,741
kWh
|
$388
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $21,582 | $19,824 |
$11,063
244,139
kWh
|
$15,853
-
kW-mo/yr
|
$(-5,334.0)
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs