ITAC Assessment: WI0303
ITAC logo
ITAC Assessment: WI0303
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Aerosol Products
NAICS
n/a
SIC 2842: Specialty Cleaning, Polishing, and Sanitation Preparations
Sales Range $10
M
to 50
M
# of Employees 120
Plant Area 104,580
ft2
Annual Production 40,000,000
pieces
Production Hrs. Annual 2,125
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $72,744 1,691,383
kWh
Electricity Demand $83,237 6,812
kW-mo/yr
Electricity Fees $3,298 -
Natural Gas $85,369 22,560
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $21,582 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.1311: Replace electrically-operated equipment with fossil fuel equipment $13,381 $15,000 $8,725
192,556
kWh
$12,951
-
kW-mo/yr
$(-8,295.0)
-
MMBtu
02 2.7142: Utilize higher efficiency lamps and/or ballasts $3,215 $3,484 $1,460
32,239
kWh
$1,755
-
kW-mo/yr
-
03 2.1233: Analyze flue gas for proper air/fuel ratio $2,961 $500 - - $2,961
-
MMBtu
04 2.4221: Install compressor air intakes in coolest locations $1,329 $840 $570
12,603
kWh
$759
-
kW-mo/yr
-
05 2.4111: Utilize energy-efficient belts and other improved mechanisms $696 - $308
6,741
kWh
$388
-
kW-mo/yr
-
TOTAL RECOMMENDED $21,582 $19,824 $11,063
244,139
kWh
$15,853
-
kW-mo/yr
$(-5,334.0)
-
MMBtu
TOTAL IMPLEMENTED - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs