ITAC Assessment: WI0299
ITAC logo
ITAC Assessment: WI0299
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Polystyrene insulation and packaging foam
NAICS
n/a
SIC 3086: Plastics Foam Products
Sales Range $10
M
to 50
M
# of Employees 80
Plant Area 131,250
ft2
Annual Production 12,000,000
lb
Production Hrs. Annual 7,200
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $53,035 1,481,536
kWh
Electricity Demand $52,403 4,296
kW-mo/yr
Electricity Fees $1,693 -
Natural Gas $127,709 30,688
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $103,657 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $27,356

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings
01 4.441: Install automatic packing equipment $36,166 $7,000 $(-202.0)
(-5,275)
kWh
$(-432.0)
-
kW-mo/yr
- $36,800
02 2.3131: Reschedule plant operations or reduce load to avoid peaks $18,337 - - $19,137
-
kW-mo/yr
- $(-800.0)
03 3.6126: Direct waste gasses to boiler combustion air $16,400 $10,000 - - $16,400
-
MMBtu
-
04 2.2442: Preheat combustion air with waste heat $15,359 $10,000 - - $15,359
-
MMBtu
-
05 4.444: Install system to collect scrap $8,748 $12,000 $(-20.0)
(-586)
kWh
$(-432.0)
-
kW-mo/yr
- $9,200
06 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $6,439 $16,400 $6,439
170,868
kWh
- - -
07 2.1233: Analyze flue gas for proper air/fuel ratio $1,424 $500 - - $1,424
-
MMBtu
-
08 2.4221: Install compressor air intakes in coolest locations $784 $740 $488
12,896
kWh
$296
-
kW-mo/yr
- -
TOTAL RECOMMENDED $103,657 $56,640 $6,705
177,903
kWh
$18,569
-
kW-mo/yr
$33,183
-
MMBtu
$45,200
TOTAL IMPLEMENTED $27,356 $23,240 $468
12,310
kWh
$(-136.0)
-
kW-mo/yr
$17,824
-
MMBtu
$9,200
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs