ITAC Assessment: WI0269
ITAC logo
ITAC Assessment: WI0269
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Enclosure Boxes for electric switchgear
NAICS
n/a
SIC 3444: Sheet Metal Work
Sales Range $10
M
to 50
M
# of Employees 230
Plant Area 300,000
ft2
Annual Production 0
units
Production Hrs. Annual 5,600
hrs
Location (State) Wisconsin

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $408,921 9,166,764
kWh
Electricity Demand $150,210 20,185
kW-mo/yr
Electricity Fees $1,364 -
Natural Gas $229,418 62,305
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $206,030 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $155,248

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Other Liquid (haz) Savings Primary Raw Material Savings Water Consumption Savings
01 3.2123: Convert to high volume low pressure (hvlp) paint guns $128,670 $10,000 - - - - $6,370
-
gal
$122,300 -
02 2.8121: Apply for tax-free status for energy purchases $22,707 - - - $22,707 - - - -
03 3.4114: Replace city water with recycled water via cooling tower $16,770 $25,000 $(-3,630.0)
(-83,529)
kWh
- - - - - $20,400
-
Tgal
04 3.8142: Distill contaminated solvents for reuse $14,920 $22,000 - - - - $5,620
-
gal
$9,300 -
05 2.7243: Improve air circulation with destratification fans / other methods $5,044 $17,980 $(-607.0)
(-22,860)
kWh
- - $5,651
-
MMBtu
- - -
06 2.3135: Schedule routine maintenance during non-operating periods $4,367 - - $4,367
-
kW-mo/yr
- - - - -
07 2.3132: Recharge batteries on during off-peak demand periods $3,269 - - $3,269
-
kW-mo/yr
- - - - -
08 2.3132: Recharge batteries on during off-peak demand periods $2,458 $7,500 - $2,458
-
kW-mo/yr
- - - - -
09 2.2621: Modify refrigeration system to operate at a lower pressure $1,973 $6,000 $924
34,584
kWh
$1,049
-
kW-mo/yr
- - - - -
10 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,653 $180 $1,124
42,204
kWh
$529
-
kW-mo/yr
- - - - -
11 2.7142: Utilize higher efficiency lamps and/or ballasts $1,692 $825 $1,151
43,083
kWh
$541
-
kW-mo/yr
- - - - -
12 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,014 $2,526 $598
22,274
kWh
$416
-
kW-mo/yr
- - - - -
13 2.6218: Turn off equipment when not in use $968 - $968
46,893
kWh
- - - - - -
14 2.3131: Reschedule plant operations or reduce load to avoid peaks $525 - - $525
-
kW-mo/yr
- - - - -
TOTAL RECOMMENDED $206,030 $92,011 $528
82,649
kWh
$13,154
-
kW-mo/yr
$22,707 $5,651
-
MMBtu
$11,990
-
gal
$131,600 $20,400
-
Tgal
TOTAL IMPLEMENTED $155,248 $50,985 $1,668
62,427
kWh
$4,339
-
kW-mo/yr
- $5,651
-
MMBtu
$11,990
-
gal
$131,600 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Other Liquid (haz) Savings Primary Raw Material Savings Water Consumption Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs