Assessment Year | 1995 |
---|---|
Principal Product | Forgings (hand tools) |
NAICS |
n/a
|
SIC | 3423: Hand and Edge Tools, Except Machine Tools and Handsaws |
Sales Range | $5 M to 10M |
# of Employees | 49 |
Plant Area |
115,000
ft2
|
Annual Production | 1,100
ton
|
Production Hrs. Annual | 2,100
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $111,051 | 1,282,532 |
kWh
|
$0.087 |
Natural Gas | $127,495 | 49,968 |
MMBtu
|
$2.55 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $11,606 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $4,981 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings |
---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,254 | $270 |
$3,254
37,515
kWh
|
- | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $891 | $3,960 |
$891
10,258
kWh
|
- | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $470 | $909 |
$470
5,569
kWh
|
- | - | |
04 | 2.2515: Use optimum thickness insulation | $1,323 | $1,461 | - |
$1,323
-
MMBtu
|
- | |
05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $764 | - |
$764
8,792
kWh
|
- | - | |
06 | 2.3132: Recharge batteries on during off-peak demand periods | $404 | - |
$404
-
kWh
|
- | - | |
07 | 3.4114: Replace city water with recycled water via cooling tower | $4,500 | $7,000 | - | - |
$4,500
-
Tgal
|
|
TOTAL RECOMMENDED | $11,606 | $13,600 |
$5,783
62,134
kWh
|
$1,323
-
MMBtu
|
$4,500
-
Tgal
|
||
TOTAL IMPLEMENTED | $4,981 | $1,731 |
$3,658
37,515
kWh
|
$1,323
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs