ITAC Assessment: WI0250
ITAC logo
ITAC Assessment: WI0250
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1995
Principal Product Screen Printing
NAICS
n/a
SIC 2759: Commercial Printing, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 85
Plant Area 42,000
ft2
Annual Production 0
units
Production Hrs. Annual 4,250
hrs
Location (State) Wisconsin

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $58,469 1,141,852
kWh
Natural Gas $6,508 1,448
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $14,041 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,705

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Other Liquid (haz) Savings Administrative Changes Savings
01 2.8121: Apply for tax-free status for energy purchases $3,196 - - - $3,196
02 2.3131: Reschedule plant operations or reduce load to avoid peaks $2,543 $2,000 $2,543
49,531
kWh
- -
03 2.7135: Install occupancy sensors $440 $300 $440
8,499
kWh
- -
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $162 - $162
3,224
kWh
- -
05 3.8142: Distill contaminated solvents for reuse $5,930 $20,000 $(-200.0)
(-3,810)
kWh
$6,130
-
gal
-
06 3.6192: Use a less expensive method of waste removal $1,770 - - - $1,770
TOTAL RECOMMENDED $14,041 $22,300 $2,945
57,444
kWh
$6,130
-
gal
$4,966
TOTAL IMPLEMENTED $2,705 $2,000 $2,705
52,755