ITAC Assessment: WI0113
ITAC logo
ITAC Assessment: WI0113
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1991
Principal Product HEAVY MACHINERY ASSEMBLY
NAICS
n/a
SIC 3547: Rolling Mill Machinery and Equipment
Sales Range $5
M
to 10
M
# of Employees 80
Plant Area
n/a
Annual Production 500
pieces
Production Hrs. Annual 7,200
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $104,433 1,567,995
kWh
Wood $95,884 163,830
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $45,722 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.8113: Purchase gas directly from a contract gas supplier $28,726 $500 - $28,726
-
MMBtu
02 2.7447: Install vinyl strip / high speed / air curtain doors $13,347 $5,500 - $13,347
-
MMBtu
03 2.7494: Install storm windows and doors $2,933 $8,643 - $2,933
-
MMBtu
04 2.4133: Use most efficient type of electric motors $174 $287 $174
2,638
kWh
-
05 2.7142: Utilize higher efficiency lamps and/or ballasts $130 $180 $130
879
kWh
-
06 2.6121: Reduce hot water temperature to the minimum required $236 - $236
3,517
kWh
-
07 2.4111: Utilize energy-efficient belts and other improved mechanisms $176 - $176
2,638
kWh
-
TOTAL RECOMMENDED $45,722 $15,110 $716
9,672
kWh
$45,006
-
MMBtu
TOTAL IMPLEMENTED - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs