ITAC Assessment: WI0041
ITAC logo
ITAC Assessment: WI0041
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1988
Principal Product SANITARY PAPER PRODUCTS
NAICS
n/a
SIC 2676: Sanitary Paper Products
Sales Range $10
M
to 50
M
# of Employees 130
Plant Area
n/a
Annual Production 12,000
ton
Production Hrs. Annual 6,000
hrs
Location (State) Wisconsin

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $113,878 2,050,997
kWh
Natural Gas $46,936 9,815
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $17,422 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $17,422

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.4312: Improve lubrication practices $7,141 - $7,141
128,664
kWh
- -
02 2.4111: Utilize energy-efficient belts and other improved mechanisms $2,945 - $2,945
53,048
kWh
- -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $6,418 $11,967 $6,418
115,475
kWh
- -
04 2.1311: Replace electrically-operated equipment with fossil fuel equipment $750 $1,000 $1,185
21,395
kWh
$(-435.0)
-
MMBtu
-
05 2.1233: Analyze flue gas for proper air/fuel ratio $168 $500 - $218
-
MMBtu
$(-50.0)
TOTAL RECOMMENDED $17,422 $13,467 $17,689
318,582
kWh
$(-217.0)
-
MMBtu
$(-50.0)
TOTAL IMPLEMENTED $17,422 $13,467 $17,689
318,582
kWh
$(-217.0)
-
MMBtu
$(-50.0)
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs